Page 17 - SISK NEWS JULY 2015
P. 17

Platform alteration

Lympstone Commando Station

Lympstone Commando Station in Devon is quite                    The slabs were loaded in 26 minutes and the RRV
        a unique place. It’s a rare example of a passenger      departed for site 25 minutes ahead of schedule.
        station not open to the general public as it’s
 exclusively for the use of visitors to the Royal Marine        02.00: The first RRV turned up at Lympstone
 Commando Training Centre.                                      Commado Station 30 minutes later than programmed,
                                                                the first slab was removed and replaced easily.
   However, it is the property of Network Rail, and in          This was then repeated for the next four, the old
 August 2014 we successfully tendered to replace 21             slabs loaded onto the trailer and taken to Exton for
 precast concrete platform slabs and undertake repairs          unloading. The second RRV then arrived at Lympstone
 to the trestles on the platform.                               Commando, the first returned from Exton, and the
                                                                team were back on schedule. RRV 1 then started to
   As you would expect, safety is the primary concern           remove the remaining slabs and load the trailer, and
 on a working railway line. To gain access we booked            RRV 2 lay the new slabs. When all the slabs were
 possessions with Network Rail twelve weeks in                  removed RRV 1 took them to Exton for unloading into
 advance. This covered everything from our means of             the compound.
 communication, the isolations required, the number of
 people on site and equipment that would be used. And           04.30: RRV 2 finished placing the slabs 90 minutes
 six weeks in advance the order was placed with Rail            ahead of programme.
 Drainage Ltd who have their own rail plant user license
 to operate rail-road vehicles (RRVs) in possessions.           Steve Brimacombe, who managed the project so
                                                                successfully, said ‘This project had to run to a very tight
   Network Rail required a minute by minute                     timeframe. The onsite team ensured that not only did
 programme to reassure them that the work would                 we finish ahead of schedule, but on budget and to a
 not overrun. This was supplied and provided the                high specification. I’m sure the passengers at Lympstone
 reassurance it could be done in one shift, with 1 hour         Commando Station will appreciate all our efforts.’
 11 minutes float time. The time frame was tight, and
 here’s how the night played out:

 22.00: On 7th March, the 21 strong team, along with
 the road-rail vehicles, met at Exmouth access point.
 Inductions and briefings were carried out and a
 Controller of Site Safety was on hand to protect all
 those involved whilst on railway. Four of the team
 then went to Exton Station by road, unloaded all the
 lights and small tools and placed them on hand trollies.
 These were then pushed to Lympstone Command
 Station by hand along the cycle path.

 00.30: Possession was due to start.

 00.45:	We finally got permission to begin, 15 minutes
 late. At Lympstone this meant erecting the lights,
 breaking out the mortar joints to the existing slabs and
 installing five sets of lifting eyes into the existing slabs.

00.50: Back at Exmouth the first RRV propelled
away from the access point so that the telehandler (a
forklift with telescopic reach) could pick up slaps and
load them on to the trailers. The RRV and trailer were
then coupled together. This took 20 minutes longer
than programmed.

01.45: The 1st RRV and loaded trailer left to go to
Lympstone Commando Station. This allowed the second
RRV and two trailers to get loaded with the remaining 16
slabs. As the track is only a single line it meant they had
to follow each other rather than work simultaneously.

                                                                Sisk News | July 2015 17
   12   13   14   15   16   17   18   19   20   21   22