Secunderabad end. This location has 3 tracks
                                                                                             with cross overs. It is located in built up area
                                                                                             with    private     houses    on     both    sides
                                                                                             (Kundanbagh & Brahmanwadi areas).
                                                                                             From the joint inspection note it is concluded
                                                                                             that it is feasible for Railways to provide RUB
                                                                                             within railway boundaries with a size of 5m
                                                                                             width x  2.5m height.  Being BMT yard
                                                                                             approach, relocation of OHE portals, S&T
                                                                                             installations is also involved.
                                                                                             For providing approach roads by GHMC, land
                                                                                             acquisition is involved and existing  private
                                                                                             buildings are to be relocated.
                                                                                             Approximate cost of this work within railway
                                                                                             boundary is Rs.5 Cr.  and can be taken up by
                                                                                             Railways on  full  deposit  terms from state
                                                                                             government.  Approach roads, drainage,
                                                                                             should be taken care  by State Government at
                                                                                             its own cost.  Revised estimate according to
                                                                                             USSR-2019 is being  prepared and  the same
                                                                                             shall be advised to   State  officials  at the
                                                                                             earliest.