Bonaberi and Figuil
        World Class EI

        Faster lockout, safer work                                                                           CAMEROON


        Opportunity             Results                                                                          Cement
        To reinforce Energy     •  22 VCS installed across
        Isolation safety, a solution   7 bucket elevators and
        was needed to cut errors   1 belt conveyor
        and shortcuts while     •  Zero EI-related incidents
        making isolation quicker   on affected equipment
        and easier. The aim: safer   •  25% faster inspection
        practices with higher    and maintenance
        efficiency in inspections
        and maintenance.

        Solution
        22 Visual Cut-Off
        Switches (VCS) were                                                                             Xavier Legrand
        installed at inspection                                                                             CEO
        and work points,
        enabling direct isolation
        of conveyors and
        bucket elevators. This
        simplified execution and
        accelerated the process
        while ensuring safety.
        Cost: 19 kCHF (22 VCS)                                                                          Amine Derridj
        Timeline: 10 months                                                                            Industrial Director








                                                                                                                    101