Page 112 - Zero is Possible - Volume 3
P. 112

Sokhna
        World Class EI

        EI station: Last stop before

        safe energy isolation                                                                                EGYPT  Cement


        Opportunity              Cost: 30 kCHF
        Standardizing energy     Timeline: 9 months
        isolation across all plant
        zones to reduce incidents,   Results
        while simplifying access to   •  Covered 100% of plant
        tools and documentation   and quarry zones with EI
        for safer, more efficient   Stations
        operations.              •  Engaged nearly 350
                                  employees in the energy
        Solution                  isolation process
        Four EI Stations were    •  Formalized and                                                     Khaled El Dokani
        strategically placed close   standardized energy                                                    CEO
        to all key work zones,    isolation procedures for
        equipped with all necessary   major equipment
        materials and documents   •  Achieved zero errors in
        for authorization and     energy isolation activities,
        validation of energy      improving management
        isolation. Each station   control and tool usage
        contains the tools and
        resources required to
        perform effective energy                                                                       Mohamed Gamieh
        isolation.                                                                                       Head of HSE