P. 252
Out sourcing of
PSI activities -No. No proposal initiated
10 of TSS regions with 1 -- -- due to punctuality of
population of trains
SPs/SPs/AT's etc.
Replacement of
OHE masts with
less contact wire
height due to
11 raising of track 3 3 0 Work Completed.
(due to top
attachment of CL
reaching max.
limit)
Status of Maintenance of OHE Assets:
ि
ू
े
िावषक Target Done वकए गए शड्यल ं का
क्र.सं. लक्ष् Up to up to संचयी प्रविशि Cum.
S.No. वििरण Description Yearly Oct- OCT 22 % of schedules
Target 2022 done.
न
1 टर्आउट Turnouts 1124 656 775 118%
2 क्रासओवर Crossovers 338 197 238 121%
े
े
ु
सक्शर् इर्सलटर Section
3 989 577 728 126%
Insulators
4 पीटीएफई PTFE 79 46 129 280%
5 एटीडी का एओएच AOH OF ATDs 4305 2511 3094 123%
6 एटीडी का पीओएच POH of ATDs 630 368 439 119%
आईओएल का एओएच AOH of 556 324 305 94%
7
IOL 38 22 45 203%
ू
यआईओएल का एओएच AOH of 1491 870 1015 117%
8
UIOL 181 106 122 116%
9 सीएल का एओएच AOH of CLs 15701 9159 10335 113%
10 सीएल का आईओएच IOH of CLs 18898 11024 12499 113%
े
11 आईसोलटर Isolators 1006 587 1579 269%
े
ु
इर्सलटर की साफ-सफाई
12 132098 77057 69100 90%
Insulator Cleaning
250