Page 249 - GM E-BOOKLET 2022
P. 249
b) Performance Statistics:
PCEE Action plan Items 2022-23:
S.N Item Target Work Balance Remarks
o Done
Provision of
Packing saddles in Work being carried out
1 2500 1127 1373
Catenary during the maintenance.
suspension clamps
Insulators procurement
Replacement of proposed in LSWP (1180
2 over Aged 10127 497 9630 Nos) and Umbrella (2800)
insulators works. (Send to HQ on
18.10.2022)
Provision of 160
sq.mm jumper wire Procurement of 1031/3 PG
in place of 105
3 101 29 72 clamps processed on
sq.mm jumper wire 06.11.2022.
for all isolators on
main line .
Availability of All the filed units are
sleeper type
4 38 0 38 advised to fabricate the
temporary masts 2 masts.
each per depot .
11.11.2022 is the due date
Improving Ah
battery capacity for tender opening.
5 of switching 11 0 11 (SSPs(07):JET,PTKP,KOLR,PD
stations with more PL,MAGH,RGPM,MMZ)
KYOP,OPL,RLW,
(SPs(04):
than 8 BM's/CB's.
MCI)
Regularly locations are
being monitored and no
rusted locations were
Replacement of identified, Zinc coating
locally spray was done by
6 manufactured 23 0 23 releasing the load in each
dwarf mast guy
rods. location. Out of 23, 5
locations are in Private
sidings (KCS siding-RDM,
BDCR-RUGS siding (04).
247