c)     Energy Consumption vs Energy Charges:











                        Andhra Pradesh TRANSCO                         Telangana TRANSCO


           Open Access Status:

           Electrical Traction Distribution has initiated the process for the Open
           Access from power supply utilities through REMCL to get power at a

           cheaper rate. For this, Availability Based Tariff meters installation and
           SCADA (Supervisory Communication and Data Acquisition) system has
           been processed with TRANSCO. Total Rs. 16.86 crores has been paid to
           TRANSCOs for providing ABT meters and 1.3 crores has been paid for

           Data Acquisition System.

           TSS wise Status of ABT meter work:


           ABT meters erection work is envisage going for open access. 21 Crores
           Payment made to SEBs. The status of work at different TSS is enumerated
           below.


                                                                              Status  of   Any      other
             S.    Name       of  Stat   Status of ABT  Provision of E-1      related      related
             No                                                               Civil
             .     the TSS        e      meters            Channel            works  @     works
                                                                                           started
                                                                              TSS

                                         Tender                                            Equipment
                   Kondapalli            floated     for  Commissioned  Complet            erection
              1                    AP
                   (KI)                  ABT  meters  by BZA Division  ed                  work
                                         by APSEB.                                         completed

                                         Meters                                            Equipment
                   Bonakalu              tendering                            Complet      erection
              2                     TS
                   (BKL)                 work  under  Commissioned  ed                     work
                                         progress          on 15.05.2020                   completed

                                         Meters                                            Equipment
                   Dornakallu            tendering         Commissioned  Complet           erection
              3                     TS
                   (DKJ)                 work  under  on 09.05.2020           ed           work
                                         progress                                          completed