Pencapaian Program Prioritas RKAP tahun 2019 The priority programs are as follows: Performance Highlights Ikhtisar Kinerja
Kap/
Proyek Lokasi Satuan Jumlah Unit Total Keterangan Progres
No
Project Location Unit Number Cap/ Total Description Progress
Unit
I Pembangkit | Generator
1 Studi FS & Pengadaan Kijang – MW 2 65 130 Mulai Proses studi oleh PUSENLIS. Namun sampai
Lahan PLTU di Pulau Bintan Pengadaan akhir tahun 2019 belum ada penugasan
Bintan Juni 2019 Report to Shareholder and Stakeholder
FS & Land Acquisition Study process by PUSENLIS. However, until the
Study for PLTU in Starting end of 2019 there was no assignment
Bintan Island Procurement Laporan Kepada Pemegang Saham & Pemangku Kepentingan
June 2019
2 Program LTSA MPP Tersebar MW 20 25 500 19 Januari Program LTSA MPP yang telah dilaksanakan
LTSA MPP program 8 Lokasi 2019 Tahun 2019 :
Spread 1. Pekerjaan Borescope Inspection (BSI) di
over 8 January 19, TM#1 dan TM#4 PLTG MPP 4 x 25 MW Tarahan
locations 2019 – Lampung
2. Pekerjaan Borescope Inspection (BSI)
di TM#1 dan TM#3 PLTG MPP 3 x 25 MW
Balaipungut – Duri
3. Pekerjaan Borescope Inspection (BSI) di
TM#1 PLTG MPP 2 x 25 MW Air Anyir – Bangka
4. Pekerjaan Borescope Inspection (BSI) di
TM#1 PLTG MPP 25 MW Gunung Sitoli – Nias Company Profile Profil Perusahaan
5. Pekerjaan Borescope Inspection (BSI) di
TM#1 dan TM#3 PLTG MPP 3 x 25 MW Paya
Pasir – Medan
6. Pekerjaan Borescope Inspection (BSI) di
TM#1 PLTG MPP 2 x 25 Jeranjang - Lombok
The LTSA MPP program that has been
implemented in 2019: Business Support Review Tinjauan Pendukung Bisnis
1. Borescope Inspection (BSI) work at TM #
1 and TM # 4 PLTG MPP 4 x 25 MW Tarahan
- Lampung
2. Borescope Inspection (BSI) work at TM # 1
and TM # 3 PLTG MPP 3 x 25 MW Balaipungut
- Duri
3. Borescope Inspection (BSI) work at TM # 1
PLTG MPP 2 x 25 MW Air Anyir - Bangka
4. Borescope Inspection (BSI) work at TM # 1
PLTG MPP 25 MW Gunung Sitoli - Nias
5. Borescope Inspection (BSI) work at TM # 1 Management Discussion & Analysis Analisa & Pembahasan Manajemen
and TM # 3 PLTG MPP 3 x 25 MW Paya Pasir
- Medan
6. Borescope Inspection (BSI) work at TM # 1
PLTG MPP 2 x 25 Jeranjang - Lombok
3 Pengadaan Tg Balai MW 2 5 10 Agustus Telah dilakukan penandatanganan MOU
Pembangkit berbasis Karimun 2019 kerjasama pembangkitan berbasis LNG 10
LNG di sekitar August 2019 MW di Tanjung Balai Karimun pada tanggal 26
kepulauan Riau Agustus 2019
Procurement of LNG- An MOU was signed on a 10 MW LNG-based
based power plants generation cooperation in Tanjung Balai Good Corporate Governance Tata Kelola Perusahaan
around the Riau Karimun on August 26, 2019
Islands
4 Operation & Tersebar MW 2 50 100 2019 Proses negosiasi harga dengan PLN UIW Babel
Maintenance Spread
Pembangkitan Price negotiation process with PLN UIW Babel
Generation Operation
& Maintenance
II Transmisi & Gardu Induk | Transmission & Substation Risk Management Manajemen Risiko
1 Pembangunan Sei Kmr 5,5 Mulai Pelelangan ditunda sampai dengan kepastian
GIS Nagoya & Phi Harapan konstruksi lahan clean and clear minimum 70% (16 tower)
Connection Transmisi – Sept 2019 dan akan di tindak lanjut oleh tim pembebasan
150 kV Harapan – Nagoya lahan
Nagoya – Baloi – Baloi Started
construction The auction is postponed until the land clearing
Development of Sept 2019 is confirmed by a minimum of 70% (16 towers)
GIS Nagoya & Phi and will be followed up by the land acquisition
Connection 150 kV team
Transmission Harapan Corporate Social Responsibility Tanggung Jawab Sosial Perusahaan
- Nagoya - Baloi