Page 357 - GM E-Booklet Dec-2022
P. 357
HYDERABAD DIVISION - 12/12/2022
Total No.of
Sl. PH No.of Works in No.of Works in No.of Works in No.of Works in No.of Works Total
No Y-o-S Works Estimate Stage Tender stage Progress stage Phy.Comp.Stage FCC Stage Wks
Sanctioned
PB / LS PB / LS PB / LS PB / LS PB / LS PB / LS
LAW WP DRM LAW WP DRM LAW WP DRM LAW WP DRM LAW WP DRM LAW WP DRM
2013-14 1 1 1
2015-16 1 1 1
2016-17 1 3 1 3 4
2017-18 1 9 1 2 7 10
Track
5 31 2018-19 1 8 4 1 4 9
Renewals
2019-20 3 3 2 3 1 6
2020-21 4 4 4
1
2
0
2
2
-
2
2021-22 9 9 9 9 9 9
2022-23 4 8 1 8 3 12
Total 56 25 12 19 1 8 3 18 2 7 3 10 4 56
2018-19 2 2 2
6 32 Bridges 2020-21 1 1 1
2021-22 1 1 1
Total 4 2 2 2 2 4
2019-20 1 1 1
7 33 S&T 2021-22 3 3 3
2022-23 1 1 1
Total 5 1 4 1 1 3 5
2017-18 1 1 1
2018-19 3 1 2 3
8 36 OEW 2019-20 1 1 1
2021-22 9 1 1 8 1 10
2022-23 9 2 6 2 1 9
Total 24 22 2 7 2 10 1 1 3 1 24