PLAN HEAD - 2900 (RSW / LEVEL CROSSINGS)
SN PH PROJECT PH Y-o-S PB Short Name of Work Alloc. Last Sanc Exp. upto Exp. Exp. Anti. Est. %age REMARKS Status
SN ID Item Cost March during upto TDC of Status Phy.
(PB,LB, prog
DRM) '22 2022- date Rly of Rly
2023 portion
9 1 11.03.29.18. 29 2018- - Hyderabad division : improvements to Level S.Fund 15851 18234 0 18234 31/03/ RE under 85 work is in progress at NI- LC gates TDC 31/03/2023 WIP
prep.
4.52.005 2019 Crossing Gates Section. 2023
10 2 11.03.29.19. 29 2019- LB- MUE-SC-DHNE, JKM-BDHN & GWD-RC - S.Fund 34334 22609 1049 23658 31/03/ Det. Est. 20 Work in progress. TDC 31/03/2023 WIP
3.52.001 2020 60 Improvements to gate lodges, 2023 Sanc.
Construction/Improvements to toilets, water supply
arrangements at gate lodges,
11 3 11.03.29.19. 29 2019- - Hyderabad division - Provision of smart real time S.Fund 7489 4865 0 4865 31/03/ Det. Est. 35 Work Temporerly kept under abeyance. TDC WIP
4.52.001 2020 gate position and auto PN system at non- 2023 Sanc. 31/03/2023
interlocked LCs.
12 4 11.03.29.20. 29 2020- LB- Hyderabad Division-Interlocking of LC gate S.Fund 7148 3744 992 4736 31/12/ Det. Est. 98 Work physically completed. Final bill under PHC
3.52.001 2021 63 No.189A at Km 448/8-9 between NVT-JKM 2022 Sanc. process.TDC = 31.12.2022.LOA issued on (FuP)
stations. 30.11.2020
13 5 11.03.29.21. 29 2021- - SC-DHNE Section: Replacement of Mechanical S.Fund 14772 0 1933 1933 30/06/ Det. Est. 20 LC 73 commissioned on 08.09.2022.Remaining WIP
4.52.001 2022 operated Lifting barrier with Electrical operated 2023 Sanc. gates,work is under process. TDC: 31/03/2023. LOA
lifting barrier at 5 interlocked LC gates (Traffi issued on 05.03.2022
14 6 11.03.29.21. 29 2021- - Hyderabad Division Rehabilitation of worn out S.Fund 4616 0 4108 4108 30/06/ Det. Est. 80 Out of 10 LC gates 04 gates (LC 60,61,219 & 228) are WIP
Sanc.
4.52.002 2022 Interlocked LC gate lifting barriers 2023 completed.Remaining gates work under progress.
TDC: 31/03/2023. LOA issued on 05.03.2022
15 7 11.03.29.21. 29 2021- - Replacement of Mechanical operated Lifting barrier S.Fund 14772 619 1587 2206 30/06/ Det. Est. 0 LC gate No. 192 & 172 are commissioned. WIP
Sanc.
4.52.003 2022 with Electrical operated lifting barrier at 5 2023 Remaining 3 gates work under progress. TDC:
interlocked LC gates (Traffic) on SC-MUE Sect 31.03.2023. LOA issued on 05.03.2022.
16 8 11.03.29.22. 29 2022- - SC-MUE Sec: Widening of road width, Re-arranging S.Fund 0 0 0 31/03/ DE under 0 Detailed estimate under process. EST
3.52.001 2023 of Booms & Improvements to Road Surface at LC 2024 prep.
Gates Under ADEN/MED Section.
17 9 11.03.29.22. 29 2022- - SC-DHNE Sec: Widening of road width, Re- S.Fund 0 0 0 31/03/ DE under 0 Detailed estimate under preparation. EST
3.52.002 2023 arranging of Booms & Improvements to Road 2024 prep.
Surface at LC Gates Under ADEN/KRNT Section.