SN PH PROJECT PH Y-o-S PB Short Name of Work Alloc. Last Sanc Exp. upto Exp. Exp. Anti. Est. %age REMARKS Status
SN ID Item Cost March during upto TDC of Status Phy.
(PB,LB, prog
DRM) '22 2022- date Rly of Rly
2023 portion
79 57 11.03.30.19. 30 2019- - Hyderabad Division - Proposed Ancillary Work for RRSK 23661 11 0 11 30/09/ Det. Est. 20 MUE Sec: LOA issued for LC No: 214, Work WIP
4.52.017 2020 RUBs in lieu of LC NO. 214 & 217 2023 Sanc. Commenced, TDC 30/09/2023
80 58 11.03.30.19. 30 2019- - Hyderabad Division - Proposed Ancillary Work for RRSK 23951 7 0 7 30/09/ Det. Est. 0 Work is in Progress. LOA issued on 27/08/2021.TDC WIP
Sanc.
4.52.018 2020 RUBs in lieu of LC NO. 156 & 158 2023 30/09/2023
81 59 11.03.30.19. 30 2019- - Hyderabad division - SC-DHNE Section :-Elimination RRSK 23642 7556 0 7556 31/03/ Det. Est. 40 LC No: 120 Closed without launching. TDC WIP
Sanc.
4.52.019 2020 of Manned LC No. 120 KM 222/900-223/0 by 2023 31/03/2023
Providing RUB in between MOA-ALPR Station.
82 60 11.03.30.19. 30 2019- - Hyderabad division - SC-DHNE Section :-Elimination RRSK 23210 7 1022 1029 30/09/ Det. Est. 0 Work is in Progress. LOA issued on 27/08/2021. TDC WIP
Sanc.
4.52.020 2020 of Manned LC No. 156 @ KM 281/200-300 by 2023 30/09/2023
Providing RUB in between VDI-BVO Station.