Page 391 - GM E-Booklet Dec-2022
P. 391
SN PH PROJECT PH Y-o-S PB Short Name of Work Alloc. Last Sanc Exp. upto Exp. Exp. Anti. Est. %age REMARKS Status
SN ID Item Cost March during upto TDC of Status Phy.
(PB,L '22 2022- date Rly prog
B,DR 2023 portion of
271 15 11.03.64.19. 64 2019- LB- HYB Divn. 1. Improvements to Railway Institute at DF(2) 24323 0 3103 3103 31/03/ Det. Est. 0 Work in Progress. TDC 31/03/2023 WIP
3.52.002 2020 1123 North Lalaguda & 2. Central Hospital, Lallaguda 2023 Sanc.
Improvements to old main medical store.
272 16 11.03.64.20. 64 2020- LB- Hyderabad division - Umri -Construction of SSE Cap. 9998 9 0 9 31/03/ Det. Est. 40 Work is in Progress. TDC 31/03/2023 WIP
3.52.001 2021 1129 P.Way UMRI Office. 2023 Sanc.
273 17 11.03.64.20. 64 2020- LB- Nizamabad~~Hyderabad division - Nizamabad - Cap. 19942 2964 1870 4834 31/03/ Det. Est. 30 Work is in progress . TDC 31/03/2023 WIP
3.52.002 2021 1130 Construction of SSE(P.Way) NZB Office including 2023 Sanc.
& Store & SSE(C&W) NZB Office.
274 18 11.03.64.21. 64 2021- LB- Hyb Div: Installation of CCTV at RPF posts having RRSK 10218 3970 0 3970 31/03/ Det. Est. 80 Installation and commissioning of CCTV's at 15 RPF WIP
6.52.001 2022 1140 coverage over space meant for keeping arrested, 2023 Sanc. Post/Outpost has been completed. Supply items are
accused & interrogation of accuse/ suspects. pending. TDC 31.03.2023. LOA issued on
18.11.2021.