Page 130 - GM's Annual Inspection Booklet DEC- 2022
P. 130

i.  Energization of newly Erected OHE between MBNR  – GED:

           single BG line OHE between section MBNR and GWD (RKM – 72.70,
           TKM – 82.53)  energized and authorization given by PCEE for running electric traction
           locomotive after inspection on 27.11.2022.


























           C .Energization of Manoharabad (MOB/TSS) with incoming supply on 28.10.2022

           Manoharabad  MOB/TSS  of  132/25KV  charged  successfully  on  28.10.2022  by  extending
           132KV  supply  From  Narsapur  TSTRANSCO  sub-station (GSS).

           D .Panduranga swamy Road (PASR/TSS): Charged on 29.10.2022

           Divitipalli  TSS  of  132/25  KV  charged  successfully  on  29.11.2022  by  extending  132KV
           supply From Ankannapally TSTRANSCO sub-station(GSS).

           V. Reliability  improvement  works:

           i.  Provision of Disconnector assembly on top side of the Lightning Arrester (LA):

           As per revised SMI no. TI/SMI/0048 (Rev. 1) dated: 23.07.2021, the Disconnector assembly of LA
           should be repositionedat the Top of the LA. The Division has taken-up the work and replaced
           16no LAs modifications.
           ii. Checking of OHE with 2032mm Pantograph:

           As  per  the  instructions  from  the  Headquarters,  the  Checking  of  OHE  with  2032
           pantograph completed  in  KCG - MOB ,  KCG - UR section in HYB Division.
























                                                           128
   125   126   127   128   129   130   131   132   133   134   135