Page 380 - GM's Annual Inspection Booklet DEC- 2022
P. 380

SN PH PROJECT  PH Y-o-S PB   Short Name of Work            Alloc.  Last Sanc  Exp. upto  Exp.   Exp.   Anti.   Est.   %age  REMARKS    Status
             SN ID             Item                                       Cost  March   during   upto   TDC of   Status  Phy.
                               (PB,LB,                                                                     prog
                               DRM)                                             '22   2022-  date  Rly     of Rly
                                                                                      2023      portion
          158 11 11.03.36.21. 36 2021- LB-  HYB Divn: Upgradation of 11 Nos. 4 pole D.P   Cap.  16871  1  0  1  31/03/  Det. Est.   0  Work in progress.  WIP
               3.52.007    2022 644 structure to 4 way RMU type at various substations          2023  Sanc.
                                   of HYB divn  as a reliability improvement measure.
          159 12 11.03.36.21. 36 2021- LB-  Repl.of 11KV OH HT line with XLPE UG cable of 3   RRSK  5272  0  0  0  31/03/  Det. Est.   0  Work in progress.  WIP
               3.52.008    2022 640 C120 Sq.mm, of CKL feeder, CKL SS to Shiva                  2023  Sanc.
                                   Temples IRISET F, Golf C-Tara on age cum
                                   condition basis.
          160 13 11.03.36.21. 36 2021- LB-  Upgradation of  Pumping System including W/M,   DRF  0  0  0  0  31/03/  DE under   0  Detailed Estimate Under sanction.   EST
                                                                                                     prep.
               3.52.009    2022 636 E/M, SCADA and Remote Operation / Monitoring                2023
                                   etc. and Imp in Water pumping & Management
          161 14 11.03.36.21. 36 2021- -  Hyderabad Division::strengthening of power supply  DRF  3339  0  0  0  31/03/  Det. Est.   0  Work in progress.  WIP
                                                                                                     Sanc.
               4.52.001    2022    to officer’s colony, service building and kalarang at        2023
                                   CKL area
          162 15 11.03.36.22. 36 2022- -  Provision of solar plants (rooftop) of different   Cap.  17668  150  150  31/03/  Det. Est.   0  Work in progress.    WIP
               3.52.001    2023    capacities at 25 Railway stations over HYB division          2023  Sanc.

          163 16 11.03.36.22. 36 2022- -  Hyderabad division: Strengthening of Pre-cooling   DF(3)  0  0  0  31/03/  DE under   0  Tender opening on 06.12.2022.  TT
               3.52.002    2023    supply arrangements to pit 2,3 &4 at Kacheguda               2024  prep.
          164 17 11.03.36.22. 36 2022- -  Hyderabad: Replacement of the over aged Main   DRF  0  0  0  30/06/  DE under   0  Tender opening on 23.12.2022.  TT
               3.52.003    2023    distribution board (MDB) with MP based MCCBs at              2023  prep.
                                   ORH/SC, Lekha Bhavan & CKL Substation.
          165 18 11.03.36.22. 36 2022- -  HYB Division: Improvement  of OHE installations   Cap.  0  0  0  31/03/  DE under   0  Detailed Estimate Under Preparation  EST
               3.52.004    2023    assets over HYB division                                     2024  prep.
          166 19 11.03.36.22. 36 2022- -  HYB Division: Upgradation of existing 105 sq.mm   Cap.  0  0  0  31/03/  DE under   0  Detailed estimate Under Preparation  EST
               3.52.005    2023    jumper wire with 160 sq.mm jumper wire to suit               2024  prep.
                                   160 kmph.
          167 20 11.03.36.22. 36 2022- -  Augmentation of traction power supply   Cap.  0  0  0  31/03/  DE under   0  Detailed Estimate Under preparation  EST
               3.52.006    2023    infrastructure  over HYB Division.                           2024  prep.
          168 21 11.03.36.22. 36 2022- -  HYB Division : Replacement of masts with less   Cap.  0  0  0  31/03/  DE under   0  Detailed Estimate under Preparation  EST
               3.52.007    2023    implantation/leaning masts and rusted ACC wires.             2024  prep.