2.  TRACTION  SUB-STATIONS  POSITION:

                S.No.      Name of TSS            Commisioned on                  Feeding Zone

                   1.         DTP TSS                 23.07.2022                    HPG/SP to

                                                                                     GWD/SP
                   2.        MOB TSS                  28.10.2022                 SFX/SP to KMC

                   3.        PASR TSS                 29.10.2022                GWD/SP to RC/SP

           *. SNF/TSS of SC Division feeding from SFX/SP to HPG/SP.
           *. MRTD/TSS of SC Division feeding from NZB to BDHN.
           *. RGM/TSS of GTL Division feeding From DHNE/SP to KRNT.

           III.  Good Works done by TRD/HYB during the year 2022-23( Till Nov 30-2022) :

                    1.    Replacement of existing O portal with R portal at KCG yard due to
                          klaying of track  for IOH SHED at loc.7/25-26.
                                                                                             st
                    2.    Cross feeder elimination work done at SFX/SP to eliminate the 1   cross feeder.
                    3.    2 new masts with cantilever assembly erected at KCG yard and
                          extended 38M OHE on Engine siding to accumulate extra
                          locomotives.
                    4.    19No.  LA disconnectors provided at  MOB/TSS,  MED/SSP,  BMO/SSP, SFX/SP.
                    5.    Provided Nylon mesh on 40No. of Portals/TTC to reduce CB tripping
                          between UR and MOB.

           IV.  MILESTONE  OF TRD HYB DIVISION DURING 2022-23:

           A. Energization of newly constructed Traction sub-station
              Divitipalli(DTP/TSS): Charged on 23.07.2022

            Divitipalli TSS of 132/25KV charged successfully on 23.07.2022 by extending
              132KV supply From Timmajipeta TSTRANSCO sub-stati

           B.  Energization of newly erected OHE:

           i.  Energization of newly Erected OHE between MOB – KMC :
               Newly Erected OHE on single BG line section between MANOHARABAD –
               KAMAREDDY  (RKM:  66.37KM,  TKM:  82.53KM)  Energized  and  approved
               by PCEE/SCR on 27.10.2022.