Page 61 - Anual report STi 2022_eng
P. 61

from delayed installment payment or delayed contract   performance, and the cash inflow of the Company Group in

          renewal. Regarding the delay in the ongoing projects due to  each period may fluctuate according to the amount of work on
          the COVID-19 epidemic, the Company was also affected.  hand, project's commissioning value, progress, or completion
          The Company is well aware of this risk. Therefore, they have  of work to collect service fees according to the agreed contract

          found a way to manage the risk of financial liquidity by  and continuity in obtaining new projects.
          considering and evaluating the quality of customers before       However, the Company Group has a guideline for risk
          bidding or accepting work. When accepting work or bidding,   management in such matters by diversifying the risk from
          the Company will focus on strictly following the service     providing consulting services in various types of projects, such
          contract to ensure that the Company will be able to deliver   as condominiums, mixed-use Development projects, office

          quality work within the specified time frame to customers.    buildings, shopping centers, educational institutions, and
          In addition, the Company has prepared a business plan and   multi-purpose buildings, infrastructure works, including
          an annual budget plan, set revenue targets by type of service,   historical conservation projects that require specialized
          as well as the proportion of work from the public and private   expertise in providing services and diversifying risks from

          sectors so that the Company's management can analyze   accepting works that cover both public and private sectors that
          information and plan appropriately for accepting work or   are more diverse, such as mergers and acquisitions AEC whose
          participating in bidding for new projects. Overdue receivables   main customers are government customers.
          and pending collections are regularly followed up. Bank credit      2.2.3  Environmental and Social Risks

          lines are regularly requested to provide adequate liquidity,
          as well as to maintain current ratio and debt to equity ratio       Nowadays, there is an emphasis and attention on
          at appropriate levels.                                 environmental care and the impact of construction on the
                                                                 lives of people surrounding construction projects from many
             Risk From Income Volatility
                                                                 agencies from the government, NGO, or even the general
             Each tender for each project or institution has different   public who have been affected. This is considered the main
          procedures, regulations, and periods. There are also other   factor that will affect the completion time of construction work.
          environmental factors that may affect investment in the     For example, the government sector tends to increase the

          construction of new real estate projects of each type, such as   strictness of construction control by issuing new rules or
          economic conditions, political situation, tourism business     regulations, such as measures to control the working time
          situation, the amount of outstanding housing in the market, the   per day that are shortened, prohibiting working during holidays
          situation of the epidemic of COVID-19, including changes in   or time after sunset, or rigorous monitoring of environmental
          government policies. Therefore, it may affect the construction   impacts such as measuring dust, smoke, or noise caused by

          business. In particular, the policies that have a significant   construction. The Company Group has established guidelines
          impact are policies on budgets for construction of various     for preventing such risks as follows:
          infrastructures which affects the construction consulting        ● During the design process, the Company tries to push

          services as well, etc. These factors result in the companies not   designers both architects and engineers to design structural
          being able to clearly know the chances of winning the bidding,   systems or other components as prefabricated systems or
          including the commencement period and the amount of     use prefabricated parts as much as possible to reduce the
          construction work in an industry that may change according   construction period, which also reduces the impact on the
          to the purpose of the employer and other environmental factors   environment.

          mentioned above, including the opportunity to obtain government
          -related jobs due to government policies. Therefore, income,