          CAIRO – AL FAYOUM HSR BRIDGE INTERCITY

          CAIRO & FAYOUM – EGYPT




          PROJECT DETAILS                                                                                                          PROJECT OVERVIEW:
          Location: Giza, Egypt                                                                                                    As the main contractor of the Al Fayoum HSR Bridge Intercity Cairo & Fayoum project in Egypt, Edecs is responsible for

          Name of Client: Ministry of Transportation & Public Authority for Roads and Bridges                                      the infrastructure construction of 14,000 meters of deep foundation piles and an 80,000 cubic meter box girder concrete
          Role in Contract: Main Contractor                                                                                        deck slab reinforced with high-strength prestressing wires. Additionally, we're responsible for road and earthworks,
                                                                                                                                   including  excavation,  retaining  walls,  road  base,  asphalt  layers,  traffic  sign  systems,  and  lighting  installations.  This
          SCOPE OF WORK                                                                                                            Bridge is a link between Cairo and Fayoum, Egypt, with a 1,600-meter-long, 76-meter-wide bridge that includes a main
                                                                                                                                   bridge in both directions, two wide service bridges, and a wide long ramp.
                                         Consultant Name: ACE Moharram-Bakhoum
             BRIDGES
                                         Contract Duration: 31 Months
                                         Project Type: Bridges












     56   www.edecs.com                                                                                                                                                                                                                   57