 PROJECT DETAILS  PROJECT OVERVIEW:
 Location: Giza, Egypt  As the main contractor of the Al Fayoum HSR Bridge Intercity Cairo & Fayoum project in Egypt, Edecs is responsible for

 Name of Client: Ministry of Transportation & Public Authority for Roads and Bridges  the infrastructure construction of 14,000 meters of deep foundation piles and an 80,000 cubic meter box girder concrete
 Role in Contract: Main Contractor  deck slab reinforced with high-strength prestressing wires. Additionally, we're responsible for road and earthworks,
            including  excavation,  retaining  walls,  road  base,  asphalt  layers,  traffic  sign  systems,  and  lighting  installations.  This
 SCOPE OF WORK  Bridge is a link between Cairo and Fayoum, Egypt, with a 1,600-meter-long, 76-meter-wide bridge that includes a main
            bridge in both directions, two wide service bridges, and a wide long ramp.
 Consultant Name: ACE Moharram-Bakhoum
 BRIDGES
 Contract Duration: 31 Months
 Project Type: Bridges