PROJECT DETAILS PROJECT OVERVIEW:
Location: Giza, Egypt EDECS leads the High-Speed Rail Viaduct endeavor in Hadayek October – Giza, erecting a state-of-the-art railway
Name of Client: Ministry of Transportation & Public Authority for Roads and Bridges spanning 1750 kilometers, capable of reaching speeds up to 250 km/hr. The project encompasses Bridgeworks, which
Role in Contract: Main Contractor entail 16,000 meters of piling, extended wires for retaining wall backs, and a primary bridge structure constructed
with 40,000 cubic meters of precast prestressed concrete girders and deck slab. Moreover, Track embankment works
SCOPE OF WORK involve excavation, backfilling, laying base layers, and installing 30,000 square meters of concrete slab. Access road
development includes establishing base and asphalt layers, while road and earthworks consist of excavation, reinforced
Consultant Name: SYSTRA & SIMENS
RAILWAY
Contract Duration: 31 Months panels, retaining walls, road base, and two layers of asphalt, as well as the installation of traffic signs, curbs, and barriers.
Project Type: Railway