RPF/TC/MLY renovation work:
All renovation works pertaining to electrical are carried
out with in-house resources with replacement of 15 Nos
of 20W LED lights, 8 Nos of LED Street lights and 18 Nos
of BLDC fans. 3 No’s of Geysers provided as a new
provision.
st
Newly constructed 1 floor of Crew rest room at Gadwal – Electrical
Arrangements
st
Newly Constructed 1 floor of crew rest room
st
Following Electrical equipment has been provided in newly constructed 1 floor of
Crew rest room at Gadwal.
Sl. No. Description Capacity Qty (No.s)
1 Inverter type split AC units 1.5 Tr 13
2 5 Star Geysers 15 ltrs 07
3 Ceiling fans 50 W 36
22 W 23
4 LED indoor fittings
15 W 20
5 Reading lamps 5W 30
Net increase in connected load is 36kW.
Rail Kalarang Optimization of AC plants:
AC Plant Rail Kalarang/CKL (relocation & renovation work) - Previously condenser
units are not able to condensate upto optimal conditions due to obstruction in airflow.
All condensers units are elevated to higher level for optimal condensations there by
better cooling temperatures. Return air path also redesigned for better air
conditioning efficiency. Dampers are provided with controls for stopping the air flow
in non-running AC unit.
AC Plants before shifting of outdoor After shifting & modified Outdoor units duly
units. fabricated with M.S Channel Structure.