PLANNING


            Preliminary works programme (PWP) under traffic facilities (PH: 1600)

                                                                                                      (Rs. in 000‟)
                                                  Latest      Outlay
                                       Year of
         Sl.      Description of        Sancti    Anticip    proposed                    Status
         No            work                        a- ted        for
                                          on
                                                   Cost       2019-20
          1.  Provision of New          2010-       Cap         1,00
               crossing station at        11      16,95,0                i. Detailed Estimate sanctioned by
               Pedashapur                            0                      GM for Rs.16.95 Crs dated 5-8-
               between                                                      11. Rs.2.16 crore deposited to
               Umdanagar and                       EBR                      state Govt. Spl. Dy.collector /RR
               Timmapur on SC-                    5,00,00                   dist. nominated for processing
               MBNR section.                                                land acquisition. Gazette
                                                                            notification issued.

                                                                         ii. Railway board transferred this
                                                                            work to RVNL vide Letter
                                                                            No.2017/W-2/SCR/TF/01 Dated
                                                                            26-04-2017. This work be taken
                                                                            up along with doubling works
                                                                            between UR-MBNR.

                                                                        iii. Final approval of ESP
                                                                            communicated by CE/P&D vide
                                                                            lr no.W.573/Y/UR-TMX dated
                                                                            27.03.2019.
          2.  Provision of 04 new       2017-     38,26,0     1,00,00     ESPs of 4 new crossing stations
               crossing stations.         18         0                    with standard layout approved
                                                                          vide CE/P&D office letter dated
              i. Wanaparthy-                                              19.06.2018.
                Kaukuntla
                (18.27kms)
              ii. Monopad-Alampur                                         Railway board sanctioned revised
                (16.10 kms)                                               estimate vide letter No. 2018/W-II/
               iii. Itikiyala-Monopad                                     SCR/ TF/ 03 dated 13.02.2019 for
                (13.58 kms)                                               Standard lay out for Rs. 38.26 Cr.
               iv. Ulindakonda-
               Veldurthi(12.06
               kms)                                                       02 new stations between WPR-
                                                                          KQQ (18.27 kms), and MOA-
                                                                          ALPR (16.10 kms) has been
                                                                          prioritized for completion.  Earth
                                                                          work is in progress.
          3.  Nizamabad:                2018-     8,79,84        --       Final      approval      of     ESP
               Remodelling of yard        19                              communicated  by  CE/P&D  vide
               arrangements for                                           letter dated 13.05.2019.
               providing additional                                       SIP is under process for approval.
               platforms and one
               full length dead end                                       Tenders      called    and     Work
               spur.                                                      awarded.