Page 235 - GM booklet 2019 test
P. 235
NEW LINES:
Sl. Description of Year of Remarks /Present status
No work Sanction
1 Akkanapet – Medak 2012-13 The ESPs of Akkanapet and Medak was approved
(17.20 Kms) and works is in progress. All Tenders for 17.20 Km
has been finalized and targetted for commissioning
during 2019-20.
NI work done from 14.05.2019 to 18.05.2019 (3 days
PRE NI and 02 days NI) at Akkanapet and additional
loop line was commissioned on 18.05.2019.
2 Manoharabad – 2006-07 The ESPs of Mahoharabad to Gajwel section was
Kottapalli (148.90 approved and works is in progress. Manoharabad -
kms): Gajwel 32.00 km is targetted for commissioning
during 2019-20.
NI working from 28.05.2019 to 01.06.2019 (3 days
PRE NI and 01 day NI) at Manoharabad completed
by Const. dept. and commissioned on 01.06.2019.
3 Mahbubnagar – 1997-98 Phase-I works: Devarkadra toKrishna Works between
Munirabad (222 Devarkadra to Jaklair section completed and one
kms) train only system introduced on 25.03.2017.
The works between Jaklair to Krishna is in progress.
ESPs for running of one train only system between
Devarkadra – Jaklair - Maganur submitted by Const.
dept. has been approved by division and sent to
Hqrs.
207