Page 1 - PH-3000
P. 1
Exp. Exp. %age
PROJECT PB Item Last upto during Anticipate Phy.
SN PH Y-o-S (PB,LB,D Short Name of Work Alloc. Sanc d TDC of REMARKS Status
ID RM) Cost March 2020- Rly portion progres
'20 2021 s of Rly
11.03.30.18. 30 2018- - SC-MUE :- Elimination of manned Level RRSK 24830 0 189 31/05/2022 15 Boxes casting completed. Launching to be done. TDC WIP
1 4.52.020 2019 crossing gate Nos.218 by providing RUB. 31/05/2022.
11.03.30.18. 30 2018- - SC-MUE Section :-Elimination of manned Level RRSK 24671 4389 90 30/06/2022 20 Box casting completed. Launching to be done. TDC 30/06/2022. WIP
2 4.52.022 2019 crossing gate Nos.186 by providing RUB
11.03.30.18. 30 2018- - SC-MUE Sec:Elimination of manned Level RRSK 24851 3500 4517 31/05/2022 50 Box inserted & LC closed in May'20 . Approach road work is in WIP
3 4.52.024 2019 crossing gate Nos.208 by providing RUBs Progress. TDC 31/05/2022.
11.03.30.18. 30 2018- - SC-MUE Section :-Elimination of manned Level RRSK 24581 0 3582 31/07/2022 15 Box Casting completed. Launching to be done. TDC 31/07/2022.
WIP
4 4.52.025 2019 crossing gate Nos.234A by providing RUB
11.03.30.18. 30 2018- - SC-MUE Section :-Elimination of manned Level RRSK 24816 0 3625 30/04/2022 22 Box Casting completed in July'20. Launching to be done. TDC WIP
5 4.52.026 2019 crossing gate Nos.234 by providing RUB 30/04/2022
11.03.30.18. 30 2018- - SC-MUE Section :-Elimination of manned Level RRSK 24757 0 3641 31/07/2022 22 Box Casting completed in July'20. Launching to be done. TDC WIP
4.52.027 2019 crossing gate Nos.233 by providing RUB 31/07/2022
6
11.03.30.18. 30 2018- - SC-MUE Section :-Elimination of manned Level RRSK 24821 4000 8942 31/05/2022 60 Boxes launching completed & LC closed in May'20. Approach WIP
7 4.52.028 2019 crossing gate Nos.232 by providing RUB road work is in progress. TDC 31/05/2022
11.03.30.18. 30 2018- - SC-MUE Section :-Elimination of manned Level RRSK 24625 4000 16502 31/08/2022 60 Boxes launching completed & LC closed in May'20. Approach WIP
8 4.52.029 2019 crossing gate Nos.230 by providing RUB road work is in progress.
TDC 31/08/2022.
11.03.30.18. 30 2018- - SC-MUE Section :-Elimination of manned Level RRSK 24696 17453 4980 30/09/2022 22 Boxes Casting Completed in Apr'20. Ready for launching. TDC WIP
9 4.52.030 2019 crossing gate Nos.224 by providing RUB 30/09/2022
11.03.30.18. 30 2018- - SC-MUE Section :-Elimination of manned Level RRSK 24786 0 79 31/08/2022 0 Work awarded on 29.09.2019 & yet to be started. TDC WIP
10 4.52.031 2019 crossing gate Nos.221 by providing RUB at KMs 31/08/2022
542/600-700 bet AKE-MZL.
11.03.30.18. 30 2018- - SC-DHNE:Provision of Ancillary works for RRSK 24590 9292 7657 31/07/2021 70 Drain work at LC No.105 completed. Approach road work and PHC
11 4.52.032 2019 existing RUB's in SC-DHNE Section. drainage is in progress. TDC 31/07/2021.
11.03.30.18. 30 2018- - SC-DHNE :- Elimination of manned Level RRSK 24888 8459 7220 31/08/2021 70 Box launching completed & LC closed in Jan'20 . Approach road WIP
12 4.52.033 2019 crossing gate No 71 by providing RUBs. work is in progress. TDC 31/08/2021.
11.03.30.18. 30 2018- - SC-DHNE Section :-Elimination of manned Level RRSK 24891 3700 4454 30/11/2021 22 Box casting completed in Apr'20 .Ready for launching. TDC WIP
13 4.52.034 2019 crossing gate Nos.140 by providing RUB 30/11/2021.
11.03.30.18. 30 2018- - SC-DHNE Section :-Elimination of manned Level RRSK 24786 3700 5228 30/11/2021 22 Box casting completed in May'20 . Ready for launching. TDC WIP
14 4.52.035 2019 crossing gate Nos.119 by providing RUB 30/11/2021.
11.03.30.18. 30 2018- - SC-DHNE Section :-Elimination of manned Level RRSK 24850 191 3757 30/06/2021 22 Box casting completed in May'20. Ready for launching. TDC PHC
15 4.52.036 2019 crossing gate Nos.109 by providing RUB 30/06/2021.
11.03.30.18. 30 2018- - SC-DHNE Section :-Elimination of manned Level RRSK 24862 11360 6759 30/09/2021 75 Box Launching Completed & LC closed in June'20. Approach WIP
4.52.037 2019 crossing gate Nos.112 by providing RUB Road Work completed. Drainage work is in progress. TDC
16
30/09/2021.
11.03.30.18. 30 2018- - SC-MUE:Provision of Ancillary Works for RRSK 24590 9500 3378 31/12/2021 55 Approach Road Work is Progress. TDC 31/12/2021.
WIP
17 4.52.038 2019 Existing RUB's in SC-MUE Section.