12. Carried out linking of datalogger with Control office application (COA) for reporting
                   train arrival/departure timings at Mahbubnagar & Medchal stations.














                                          Linking of datalogger with COA at MBNR & MED


               13. Existing  single  line  pushbutton  tokenless  block  instrument  between  BVO-DHNE
                   section replaced with UFSBI along with  HASSDAC of CEL make working on dual
                   media(OFC & Quad cable).















                                    Provision of UFSBI with HASSDAC at BVO-DHNE



               14. Replaced 67 nos. of worn out point machines along with ground connections.
















                                    Point machines replacement with ground connection