Page 47 - VCC 2022 Capital Plan New Binded
P. 47

PHASE ONE - PARKING LOT







                                                             The existing paved parking surface at the Valdosta Country Club was observed to exhibit cracking and
                                                             localized failure in multiple locations due to wear and tear, tree roots, lack of base material, etc.  After a
                                                             subsurface investigation, it was noted that a majority of the existing parking lot consists of less than 2" of
                                                             asphalt with little to no underlying base material. According to the subsurface investigation report, Parking
                                                             Lot 1 was noted to have 5 1/2 to 6" of soil cement base, with the remaining parking areas having no base
                                                             material.


                                                                                                                                                                                       The proposed parking
                                                                                                                                                                                       lot layout increases the
                                                                                                                                                                                       size of the parking
                                                                                                                                                                                       spots as well as the
                                                                                                                                                                                       drive aisles. The
                                                                                                                                                                                       construction will
                                                                                                                                                                                       include a new layer of
                                                                                                                                                                                       base material as well
                                                                                                                                                                                       as a new asphalt
                                                                                                                                                                                       course, suitable for the

                                                                                                                                                                                       anticipated traffic
                                                                                                                                                                                       flow.  Additionally, the
                                                                                                                                                                                       exhibit displays all new
                                                                                                                                                                                       18" curb and gutter,
                                                                                                                                                                                       both new and
                                                                                                                                                                                       revitalized interior
                                                                                                                                                                                       islands, as well as the
                                                                                                                                                                                       addition of two new

                                                                                                                                                                                       gates at entrance/exit
                                                                                                                                                                                       locations. The
                                                                                                                                                                                       proposed layout
                                                                                                                                                                                       provides a total of 192
                                                                                                                                                                                       parking spots, with the
                                                                                                                                                                                       option of overflow
                                                                                                                                                                                       parking adjacent to
                                                                                                                                                                                       the pool area and cart
                                                                                                                                                                                       barn.
   42   43   44   45   46   47   48   49   50   51   52