Page 6 - GNSCNewFinal3
P. 6

How can I
                                                          Here is the type of statuses for your awareness.
          identify the
          status of my                    •     Draft:  This  means  that  the  request  has  not  been
          request?                              forwarded to Supply Chain for Processing

                                          •     Submitted: The ticket has been sent to SC Queue for a

                                                PO request
                                          •     RFI: The Supply Chain Team has sent back the request to

                                                ask for more information if they need clarity with the
                                                request and BOM details.

                                          •     Quote  Requested  -  to  be  renamed  as  Awaiting  quote
                                                approval: This means that the Lead Engineer is currently
                                                reviewing  the  quote  and  they  will  either  approve  or
                                                reject it.

                                          •     PO Undergoing Approval: The PR has been submitted in
                                                Coupa and the budget is being approved.

                                          •     PO Issued: The PO has been issued and has been sent to
                                                suppliers for processing.

                                          •     Invoiced: The invoice has been created against the PO

                                                and Delivery in Full: The goods/services have taken place.


         How do I know
         if the goods are                     The Supply Chain Team are in touch with the supplier on a

         on their way?                        weekly basis (sometimes more frequent if required) this will
                                              be to obtain an estimated time for delivery. We will update
                                              your request with the estimated date of delivery, along with
                                              an Equinix Inbound Shipment ticket, this will be created for
                                              you so you will no longer be required to access the Internal
                                              Equinix  Customer  Portal  to  do  so.  Once  the  package  has
                                              arrived, the materials will be delivered to the designated cage

                                              if needed and the status of your request will be update to
                                              “Delivered in Full” so you will be aware that your request has
                                              been fulfilled.


         What if I have
         an issue with

         my request,                         The Supply Chain tool has an escalate button, see diagram
         who do I reach                      overleaf!
         out to?
   1   2   3   4   5   6   7   8