RINGLOCK

                       SAFETY MANUAL & USER GUIDES


                       Erection Guidelines—Steps 7 & 8



            SCAFFOLDING ERECTION GUIDELINES STEP 7


            1. As an alternative, a temporary
               (dummy) lift could be installed
               1.0m above the base of the
               scaffold. The scaffolders will
               then able to stand at the
               correct height to safely install
               the Guardrails above the first
               working platform level.




















            SCAFFOLDING ERECTION GUIDELINES STEP 8

            1. If the temporary lift (Step 7) has been used then move Planks up to working lift, add
               the toeboards which slot behind the wedge. The erection is now complete.



























                                                                                    TEMPORARY LEDGER
                                                                                    CAN BE REMOVED OR
                                                                                    LEFT IN PLACE IF ACCESS
                                                                                    WAY IS NOT REQUIRED.