Page 10 - Draft_Copy.doc
P. 10
3.7.8 Details cost of extra works
# Descriptions Unit Unit Price (LKR)
01 Brick wall 9” Square feet 260.00
02 Brick wall 6” Square feet 180.00
03 Retaining Wall Square feet 900.00
04 Concrete Cubic feet 675.00
05 Plastering Square feet 150.00
06 Rebar piece As market price
07 Slab (<800 SF) Square feet 560.00
08 Slab Square feet 485.00
09 Slab Beam (Concrete ) Cubic feet 1110.00
10 Tilling (Labor Cost) Square feet 145.00
11 Wood Works piece As design
12 Wall demolishing Square feet 50.00
13 Concrete demolishing Cubic feet 500.00
14 Plaster demolishing Square feet 65.00
15 Wood Flooring Square feet 1200.00
3. 8. Materials .
# Works Description Category Materials’ Name
01 Foundation Foundation for 3 story Rebar MELWA
building Cement Tokyo super
Mahaweli Marine
Ultratech
02 Brick Work 6 inch & 9 inch wall Rebar MELWA
10.5 ft (Height) Cement Tokyo super
Mahaweli Marine
Ultratech
Brick Ambatenna Brick
03 Slab 4 inch thickness Rebar MELWA
Cement Tokyo super
Mahaweli Marine
Ultratech
04 Retaining Wall 8 inch thickness Rebar Melbourne
Double net Cement Tokyo super
reinforcement Mahaweli Marine
Ultratech
Note:-
Contract between Owner and Builder