Page 25 - Green Builder Magazine Jan-Feb 2018 Issue
P. 25

CREDIT:  NATIONAL GUARD





















































                   Preparing for the worst. Changing weather patterns are making scenes like this Hurricane Harvey-related one all-too-common nationwide. They’re
                   also a signal flare for builders, who need to prepare even more for natural disasters.
                     7    Improper elevation of habitable space and utilities relative to flood risks
                          resulted in structural and contents damage.

                           LEVATED HOMES TEND to survive flooding much better   Bottom line: The depth is key. It should be noted, however, that
                           than those on low-lying foundations. Flood vents in   pilings do not guarantee an unscathed structure after a storm:
                           elevated reinforced block or monolithic foundations can   “A study of Topsail Island found that 98 percent of post-1986
                           save a home, if flood levels adhere to “normal” levels. But   oceanfront houses (200 of 205) remained after the hurricane.
                   E let’s assume future storm surges WILL exceed current   Ninety-two percent of the total displayed no significant damage
                   height estimates—and focus on the use of pilings.       to the integrity of the piling foundation. However, 5 percent were
                     After Hurricane Fran in 1996, FEMA conducted a study of what   found to have leaning.”
                   happened to stilt homes. The agency found that:           FEMA tested the leaning buildings to find out what happened.
                     “A significant reduction in building losses was observed in simi-  They discovered that among the leaning buildings, “none of the
                   larly sized oceanfront buildings constructed after the North Caro-  leaning pilings tested met the required piling embedment standard.
                   lina Building Code was amended in 1986 to require a minimum   Many were much shorter.”
                   embedment to 5 feet National Geodetic Vertical Datum (NGVD),   In other words, the contractors failed. Out of this research, the
                   or 16 feet below the original ground elevation, whichever is shal-  suggestion was made that pilings be embedded to a minimum depth
                   lower, for pilings near the ocean.”                     of 10 feet NGVD, without exception.

                   www.greenbuildermedia.com                                                 January/February 2018 GREEN BUILDER  23




          18-25 GB 0118 NR-Next Big One.indd   23                                                                              12/14/17   4:10 PM
   20   21   22   23   24   25   26   27   28   29   30