3.7.2 Traditional constructions
In this paragraph the cost calculation are given for the reconstruction of a damaged road. The
calculations are based on the unit prices given in paragraph 3.7.1. The construction of the
traditional construction is divided in 6 steps:
- Step 1: Excavation and preparation.
- Step 2: Leveling and pre-compaction.
- Step 3: Applying Sub-grade material.
- Step 4: Applying Sub-base material.
- Step 5: Applying Base-course material.
- Step 6: Applying Wearing course.
In appendix 4 the cost calculation is given for the steps. The total costs are presented in tables
3.14 to table 3.18 and are the construction costs summarized per Road type.
Roadtype 1: Highways
Soil type 1: Organic clays Soil type 2: Clay Soil type 3: Sandy clay Soil type 4: Sand
Step 1 Excavation/ scarifying/preparation $ 40,96 $ 40,54 $ 29,98 $ 29,98
Step 2 Leveling and precompaction $ 8,89 $ 8,89 $ 8,89 $ 8,89
Step 3 Applying Sub-grade $ 115,38 $ 115,38 $ 0,00 $ 0,00
Step 4 Applying Sub-base $ 96,15 $ 96,15 $ 115,38 $ 115,38
Step 5 Applying Base-Course $ 103,22 $ 103,22 $ 103,22 $ 103,22
Step 6 Wearing course $ 1.436,50 $ 1.352,00 $ 1.352,00 $ 1.352,00
2
TOTAL COSTS IN MEXICAN PESOS [m ] $ 1.801,09 $ 1.716,17 $ 1.609,46 $ 1.609,46
1
TOTAL COSTS IN MEXICAN PESOS [m ] $ 43.226,20 $ 41.188,07 $ 38.627,14 $ 38.627,14
Table 3.14: Summarized cost calculation Highways(traditional system)
Roadtype 2: Primary roads
Soil type 1: Organic clays Soil type 2: Clay Soil type 3: Sandy clay Soil type 4: Sand
Step 1 Excavation/ scarifying/preparation $ 40,11 $ 40,11 $ 29,56 $ 29,56
Step 2 Leveling and precompaction $ 8,89 $ 8,89 $ 8,89 $ 8,89
Step 3 Applying Sub-grade $ 115,38 $ 115,38 $ 0,00 $ 0,00
Step 4 Applying Sub-base $ 96,15 $ 96,15 $ 115,38 $ 115,38
Step 5 Applying Base-Course $ 103,22 $ 103,22 $ 103,22 $ 103,22
Step 6 Wearing course $ 1.267,50 $ 1.267,50 $ 1.267,50 $ 1.267,50
2
TOTAL COSTS IN MEXICAN PESOS [m ] $ 1.631,25 $ 1.631,25 $ 1.524,54 $ 1.524,54
1
TOTAL COSTS IN MEXICAN PESOS [m ] $ 19.574,97 $ 19.574,97 $ 18.294,50 $ 18.294,50
Table 3.15: Summarized cost calculation Primary roads(traditional system)