Sample Progress Billing:
Project: ACME Manufacturing
Final Progress Billing
No. Item Amount % Complete Progress Amount
1. General $107140 100 $107140
2. Site Work 118080 100 118080
3. Concrete 99525 100 99525
4. Masonry 44155 100 44155
5. Metals 59870 100 59870
6. Carpentry 13330 100 13330
7. Moisture Protection 65040 100 65040
8. Doors/Windows 46900 100 46900
9. Finishes 77125 100 77125
10. Specialties 7650 100 7650
11. Building System 180000 100 180000
12. Mechanical 92480 100 92480
13. Electrical 70000 100 70000
Total $982,895 $982,895.00
Deduct 10% holdback 98,289.50
Balance $884,605.50
Deduct previous billings 884,605.50
Add due from previous billings nil
Holdback amount due $98,289.50
Holdback payment due in accordance with the terms of our signed agreement