Page 17 - Panduan Simulasi Homer KKP PLTS Hybrid
P. 17

Cost Curve Assumption








             Assumption agreed by PLN MMU & NZMATES for O&M Cost




                    Assumption                Capacity                               Total

                                                          Operators


                       Hybrid                 <= 1MW                3 Persons (+ 1 Cleaning Service)

                                               >1MW                 3 Persons (+2 Cleaning Service)

                        PLTD                    24 h                              6 Persons

                                                12 h                              4 Persons

                                                  Consumable Materials


                                 PV                                      0.47% of total PV Capex

                                BESS                                    0.1% of total BESS Capex

                               Diesel                                  0.48% of total PLTD Capex