Page 4 - Newsletter SEPTEMBER 23
P. 4

1 Liverpool Street...
                                                               Works continue to progress at 1 Liverpool
                                                               Street.  Cementation Skanska  and
                                                               William Hare are currently delivering the
                                                               piling and steelwork installation for phase
                                                               1  works  in  line  with  their  programme.
                                                               The  erection  of  Tower  Crane  01  was
                                                               an important milestone for the project,
                                                               which  was  carried  out  successfully  in
                                                               August by Select and Ainscough.


                                                               Our    Limited    team  is  on  target  to
                                                               complete  the  piling  and  structural
                                                               steelwork  in  late  November  when
                                                               the  basement  excavation  bulk  dig
                                                               will  commence.  This  will  then  allow
                                                               the     basement         permanent         works
                                                               construction to start with an anticipated
                                                               contract completion in September 2024.

                                                               We are sharing fantastic updates from 1
                                                               Liverpool Street on the John F Hunt Group
                                                               LinkedIn page!  Click here to  watch the
                                                               latest video with Davinder.





        Euston Station...
        Over the weekend of 26th – 28th August,
        John F Hunt carried out partial balcony
        removal at Euston Station (Parcel Deck)
        during weekend 22 of possession.


        The section of the balcony was situated
        directly  above  Platform  15.  Due  to
        various  site  constraints,  such  as  limited
        working  space  and  existing  Network
        Rail  assets,  the  cut and lift  method
        was  selected  to  undertake  the  works,
        utilising  concrete  cutting  and  a  pick
        and carry crane. Following the balcony
        removal, we were tasked to install the
        temporary bridge,  which  consisted  of
        RMD propping and GRP decking.

        As  a  result  of  meticulous  planning
        followed by careful execution, both the
        balcony removal and temporary bridge
        installation were completed safely and
        on time. The main demolition works will
        re-commence on 18th September 2023.