Page 4 - Newsletter SEPTEMBER 23
P. 4
1 Liverpool Street...
Works continue to progress at 1 Liverpool
Street. Cementation Skanska and
William Hare are currently delivering the
piling and steelwork installation for phase
1 works in line with their programme.
The erection of Tower Crane 01 was
an important milestone for the project,
which was carried out successfully in
August by Select and Ainscough.
Our Limited team is on target to
complete the piling and structural
steelwork in late November when
the basement excavation bulk dig
will commence. This will then allow
the basement permanent works
construction to start with an anticipated
contract completion in September 2024.
We are sharing fantastic updates from 1
Liverpool Street on the John F Hunt Group
LinkedIn page! Click here to watch the
latest video with Davinder.
Euston Station...
Over the weekend of 26th – 28th August,
John F Hunt carried out partial balcony
removal at Euston Station (Parcel Deck)
during weekend 22 of possession.
The section of the balcony was situated
directly above Platform 15. Due to
various site constraints, such as limited
working space and existing Network
Rail assets, the cut and lift method
was selected to undertake the works,
utilising concrete cutting and a pick
and carry crane. Following the balcony
removal, we were tasked to install the
temporary bridge, which consisted of
RMD propping and GRP decking.
As a result of meticulous planning
followed by careful execution, both the
balcony removal and temporary bridge
installation were completed safely and
on time. The main demolition works will
re-commence on 18th September 2023.
4