61.5.2   Electrication of KR route


                        At present, on Konkan Railway, the trains are running with diesel traction. After the
                         electrication, there will be projected saving of ` 200 Crore per annum on fuel cost
                         and net saving of ` 60 Crore per annum after paying Principal and interest on loan.
                         Besides the saving, it will help in maintaining the sensitive ecological balance of
                         Western Ghats. Electrication will also improve the operating efciency of the
                         Corporation.

                   61.5.3  Construction of 8 new stations and 7 additional Loop lines


                        Due  to  this,  capacity  of  running  trains  is  expected  to  increase  without  the
                         incurrence of considerable expenditure.

                   61.5.4 Siding for MRPL, Mangalore


                        Siding trafc operational business is projected at 30 Rakes/ month of various
                         commodities like pet coke, sulphur, bitumen, polypropylene etc.

                   61.5.5 Rail Connectivity to Vizhinjam International Seaport, Kerala


                        The  work  involves  execution  of  construction  works  for  Rail  connectivity  from
                         Seaport to nearest feasible railway station. DPR has been submitted to concerned
                         authority for approval.


                   61.5.6 International Projects: PET Survey and Final Location Survey for new BG
                         line between Raxaul and Kathmandu

                        East Central Railway (ECR) have awarded Final Location Survey for new BG Line
                         between Raxaul and Kathmandu to the Corporation. Tender process by KRCL
                         through IREPS portal is progressing.


                   61.5.7 Export of Rolling stock to Nepal

                        Konkan Railway bagged the rst International order for supply of 2 (two) DEMU
                         train sets to Nepal Railway. The rakes have been manufactured at Integral Coach
                         Factory (ICF), Chennai and are kept at Sonpur in East Central Railway for delivery
                         to Nepal.
                        KRCL is also expected to receive order from Nepal Railway for Operationalizaition
                         of Jaynagar-Kurtha cross border rail link.