ERECTION/ FIXING/ JOINTING

610 INSTALLATION INSTRUCTIONS PROVIDED BY MANUFACTURER
      • Information: Provide clear and comprehensive instructions and ensure that they
          are understood by the site operatives.

630 ACCURACY OF ERECTION
      • Supporting structure: Before commencing installation of precast panels, carry out
          survey sufficient to verify that required accuracy of erection can be achieved.
          - Give notice: If the structure will not allow the required accuracy or security of
             erection.
      • Joint centres: Set out to ensure consistent joint widths.
      • Joint width: Within the length of any joint, including those interrupted by transverse
          joints, to vary by not more than 10% or nominal joint width.
          - Variations: Evenly distributed with no sudden changed.
          - General: Within recommendations of joint sealant of baffle manufacturer.
      • In-line edges in elevation: Deviation across transverse joint to vary by not more
          than 10% or nominal joint width.
      • Flat faces of adjacent panels: Offset in plan or section across any joint to vary by
          not more than 10% or nominal joint width.
      • Finished appearance: Notwithstanding tolerances stated above and in clause 420,
          panels must be square, regular, true to line, level and plane with a satisfactory fit at
          junctions.

640 FINAL FIXING
      • Approval of appearance: Obtain for each elevation prior to tightening fasteners,
          filling bed joints and dowel sockets or sealing joints.
      • Threaded fasteners: Tighten to torque figures recommended by manufacturer.
          - Restraint fixings permitting lateral movement: Do not overtighten.
      • Filling for dowel bars and recessed lifting devices: Well tamped fairly dry 1:4
          cement:sand or suitable epoxy or polyester mix.

650 MORTAR BEDDING TO PANELS ON SUPPORT STRUCTURE
      • Condition of surfaces: Clean.
      • Cavity adjoining bedding: Free of mortar.
      • Bed joint: Fully filled with dry 1:3 cement:sand mix. Well compacted.

670 OPEN DRAINED JOINTS
      • Rear seals: Airtight and watertight.
      • Baffles and flashings: Securely installed.