Page 29 - 11394_AEW_XX_XX_PP_A_0003_CO-OP PRE-CONSTRUCTION MANUAL
P. 29

2









        2A.3 Developer led project


        Internal PM








              Task                                                          SLA              Issue      Available on  Standard form
                                                                                             Method     I-Site (/)
           Stage 1  Receive Project Plan from External Project Manager      - -              Email                   Project Plan (email form)
              Attend Scheme Approval 1 meeting and review Scheme Approval 1 information
                                                                                                                      -
                                                                                             -
              presented by External Project Manager and Quantity Surveyor                                     
              Complete Scheme Approval 1 meeting minutes and issue to RAM, External Project   -  Email               Scheme Approval Minutes
              Manager, Quantity Surveyor and Format team

              Task                                                          SLA              Issue      Available on  Standard form
                                                                                             Method     I-Site (/)
              Issue Principal Designer appointment letter                   Immediately following  Email             Principal Designer Appointment Letter
                                                                            board approval
              Receive complete Principal Designer appointment letter        -                Email                   Principal Designer Appointment Letter
              Review and approve the agreed shell specification document and notify the External   -  Email          -
              Project Manager
           Stage 2  Attend Scheme Approval 2 meeting and review Scheme Approval 2 information   -  -                 -
              presented by External Project Manager and Quantity Surveyor
              Complete Scheme Approval 2 meeting minutes and issue to RAM, External Project
              Manager, Quantity Surveyor, Architect, Principal Designer and Format team  -   Email                   Scheme Approval Minutes
              Receive Cost Validation 2 [CV2] from the External Project Manager if CV2 > CV1  -  Email               Cost Validation [CV2] cost document
              Represent at FCEF if CV2 costs exceed +5% of approved CV1 costs, or outside 12   -  Email              -
              months of Board approval date
              Escalate to Head of Acquisitions for DAL uplift if CV2 exceeds Board Approval >5%   -  Email           -
              of CV1 costs
              Notify External Project Manager when scheme approved to proceed  -             Email                   -


              Task                                                          SLA              Issue      Available on  Standard form
                                                                                             Method     I-Site (/)
              Attend Exchange Meeting (on-site for Conversions only)        -                Email                   PCSD 06 – Project Exchange Form
              Receive Exchange Meeting Minutes from External Project Manager  -              Email                   Exchange Meeting Minutes
                                                                                                                      (Updated PCSD 06 – Project Exchange Form)
           Stage 3  Receive Stage 3 drawings from Architect and PCI from Principal Designer prior to   - -  Email    Stage 3 Drawings
              submission of planning applications
                                                                                                                      PCI
              Receive Dashboard Updates and Photographic Reports from Shell Monitor
                                                                                                                      Dashboard Update
                                                                                             Email
              throughout the during of the Developer’s shell construction phase                                      Photographic Report
              Attend First Site Visit [FSV] during Developer’s shell construction phase with the   -  Email          Pre-start Meeting Agenda
              design team to review project documents / information
              Receive FSV meeting minutes from External Project Manager     -                Email                   Pre-start Meeting Minutes (updated Agenda)

              Notified by Principal Contractor of novated / appointed Architect  -           Email                   -













































         2A.3   Developer led project             Internal PM                          0.0                                   11.10.19
   24   25   26   27   28   29   30   31   32   33   34