Page 34 - 11394_AEW_XX_XX_PP_A_0003_CO-OP PRE-CONSTRUCTION MANUAL
P. 34
2
2A.7 Developer led project
Principal Designer
Task SLA Issue Available on Standard form
Method I-Site (/)
Receive Principal Designer appointment letter from Internal Project Manager - Email Principal Designer Appointment Letter
Complete and return Principal Designer Appointment Letter to Internal Project 1 week Email Principal Designer Appointment Letter
Manager and External Project Manager
Undertake a desktop assessment of survey information and reports. Information 1 week - -
from desk top review to feed into PCI document
Stage 2 Attend Design Team Meeting with External Project Manager, Quantity Surveyor and - - Email Design Team Meeting Agenda
Architect
Email
Design Team Meeting Minutes (Updated Agenda)
Receive Design Team Meeting Minutes from External Project Manager
Following design team meeting produce Site Inspection Report identifying site 1 week - Site Inspection Report
hazards / design feedback and collate PCI
Receive agreed Developer shell drawings and specification from External Project - Email -
Manager
Collate and produce Pre-Construction Information document and issue to External 1 week Email PCI
Project Manager
Receive Scheme Approval 2 meeting minutes from Internal Project Manager - Email Scheme Approval Minutes
Task SLA Issue Available on Standard form
Method I-Site (/)
Receive notification from External Project manager to proceed with development of - Email -
Stage 3 information
Review the Pre-Construction Information 1 week - PCI
Stage 3 Pre-Construction Information completed and issued to the full team including; 1 week Email PCI
Construction Manager, RAM, Co-op Principal Contractor, Internal Project Manager,
External Project Manager, Quantity Surveyor, Architect and Shell Monitor
Receive Dashboard Updates and Photographic Reports from Shell Monitor - Email Dashboard Update
throughout the during of the Developer’s shell construction phase Photographic Report
Attend First Site Visit [FSV] during Developer’s shell construction phase with the - Email Pre-start Meeting Agenda
design team to review project documents / information
Receive FSV meeting minutes from External Project Manager - Email Pre-start Meeting Minutes (updated Agenda)
2A.7 Developer led project Principal Designer 0.0 11.10.19