Page 31 - 11394_AEW_XX_XX_PP_A_0003_CO-OP PRE-CONSTRUCTION MANUAL
P. 31

2









        2A.4 Developer led project


        External PM








              Task                                                          SLA           Issue        Available on   Standard form
                                                                                          Method       I-Site (/)
              Receive complete Principal Designer appointment letter        -             Email                      Principal Designer Appointment Letter
              Notify project team (Quantity Surveyor, Architect and Format) of Scheme Approval 1   1 day  Email      -
              success
              Engage with the Developer and lead the project team through negotiation with the   -  Email            -
              Developer until final shell drawings are agreed
              Attend Design Team Meeting with Quantity Surveyor, Architect and Principal   -  Email                  Design Team Meeting Agenda
              Designer
              Complete Design Team Meeting Minutes and issue to Quantity Surveyor, Architect   1 day  Email          Design Team Meeting Minutes (Updated Agenda)
              and Principal Designer
              Agree shell specification with Developer and obtain approval from Internal Project   Circa 4 weeks  Email    -
              Manager
              Issue final shell drawings and specification to Architect, Principal Designer and   1 day  Email       -
              Format team
              Receive Stage 2 information from project team                 -             Email                      Stage 2 report
           Stage 2  Review and update PCSD’s 00-04, complete PCSD 05 and issue to the Quantity   1 week  Email       PSCD 00 – Project Info
                                                                                                                      PCI
              Surveyor, along with Stage 2 information for Cost Validation 2 [CV2] to be developed
                                                                                                                      PCSD 01 – Drawing Governance Support Document
                                                                                                                      PCSD 02 – Cost Validation Request Form [CVRF]
                                                                                                                      PCSD 03 – Risk Register
                                                                                                                      PCSD 04 Key Abnormals Schedule
                                                                                                                      PCSD 05 – Acquisition and Pre-Construction Cost Summary
                                                                                                                      Stage 2 report
                                                                                                                      PCI
              Receive Scheme Approval 2 package of information from Quantity Surveyor  -  Email                      Cost Validation [CV2] cost document
                                                                                                                      Stage 2 report
              Review Scheme Approval 2 package of information and notify Quantity Surveyor of   1 day  Email         -
              any required updates prior to submission to Scheme Approval
              Attend Scheme Approval 2 meeting and present site with Quantity Surveyor  -  -                         -
              Receive Scheme Approval 2 meeting minutes from Internal Project Manager  -  Email                      Scheme Approval Minutes
              Notify RAM to proceed to exchange of contracts if CV2 is less than CV1  1 day  Email                   -
              Escalate Cost Validation 2 [CV2] to RAM and Internal Project Manager if CV2 > CV1  1 day  Email        Cost Validation [CV2] cost document
              Notified by RAM / Internal Project Manager to proceed to Stage 3 when CV2 costs   -  Email             -
              approved at FCEF or by Head of Acquisitions and RAM has exchanged contracts

              Task                                                          SLA           Issue        Available on   Standard form
                                                                                          Method       I-Site (/)
              Issue Exchange pack (including agreed shell drawings / specification and PCSD 06)   1 week  Email      PCSD 06 – Project Exchange Form
              to Shell Monitor min.1 week prior to Exchange Meeting
              Arrange and attend Exchange Meeting (on-site for Conversions only)  2 weeks  Email                     -
              Complete Exchange Meeting Minutes and issue to Construction Manager, RAM,   1 day  Email               Exchange Meeting Minutes
              Internal Project Manager and Shell Monitor                    1 day         Email                       (Updated PCSD 06 – Project Exchange Form)
              Notify Architect and Principal Designer to proceed with development of Stage 3
                                                                                                                      -
                                                                                                             
           Stage 3  information                                             -             Email                      Stage 3 Drawings
              Receive Stage 3 drawings from Architect and PCI from Principal Designer prior to
              submission of planning applications
                                                                                                                      -
              Notify Format team to review and approve the proposed Advertisements design  -  Email                  PCI
              Receive Dashboard Updates and Photographic Reports from Shell Monitor   -   Email                      Dashboard Update
              throughout the during of the Developer’s shell construction phase                                       Photographic Report
              Attend First Site Visit [FSV] during Developer’s shell construction phase with the   -  Email          Pre-start Meeting Agenda
              design team to review project documents / information
              Complete FSV meeting minutes and issue to Construction Manager, Principal   1 day  Email               Pre-start Meeting Minutes (updated Agenda)
              Contractor, Internal Project Manager, Quantity Surveyor, Architect and Principal
              Designer


























         2A.4   Developer led project             External PM                          0.0                                   11.10.19
   26   27   28   29   30   31   32   33   34   35   36