Page 35 - 11394_AEW_XX_XX_PP_A_0003_CO-OP PRE-CONSTRUCTION MANUAL
P. 35
2
2A.8 Developer led project
Shell Monitor
Task SLA Issue Available on Standard form
Method I-Site (/)
Receive Exchange pack (including agreed shell drawings / specification and - Email PCSD 06 – Project Exchange Form
PCSD 06) from External Project Manager min.1 week prior to Exchange
Meeting
Attend Exchange Meeting (on-site for Conversions only) - Email PCSD 06 – Project Exchange Form
Receive Exchange Meeting Minutes from External Project Manager - Email Exchange Meeting Minutes
(Updated PCSD 06 – Project Exchange Form)
Stage 3 Conduct site visits to inspect Developer’s shell works at intervals becoming 18-6 months pre-Practical Completion - -
site visits at 3 weekly intervals.
increasingly frequent approaching Practical Completion
6-3 months pre-Practical Completion
site visits at 2 weekly intervals.
3-0 months pre-Practical Completion
site visits at 1 weekly intervals
Issue dashboard updates / photographic records following every site visit Within 1 day of site visit Email Dashboard Update
to; Construction Manager, RAM, Co-op Principal Contractor, Internal Project Photographic Report
Manager, External Project Manager, Quantity Surveyor, Architect and
Principal Designer
Agree Practical Completion with the Developer, concluding the Pre- - Email -
Construction phase
2A.8 Developer led project Shell Monitor 0.0 11.10.19