Page 19 - 11394_AEW_XX_XX_PP_A_0003_CO-OP PRE-CONSTRUCTION MANUAL
P. 19

RAM                             External PM                                    QS                               Architect







                     Marginal site identified








                                                           Ex.PM instructs Architect
                     RAM instructs Ex.PM of                and QS (if cost appraisal                                                     Architect undertakes
                        marginal site                      is required) to undertake                                                     Stage 0 feasibility study
                                                                Stage 0






                                                                                                                                         Architect issues Stage
                                                                                                                                         0 feasibility drawing to
                                                                                                                                            Ex.PM & QS











                                                             Stage 0 feasibility                    Stage 0 feasibility
                                                             drawing received                       drawing received









                                                                                                   QS develops Stage 0
                                                                                                     cost appraisal






                                                                                                  QS issues Stage 0 cost
                                                                                                   appraisal to Ex.PM





                                                                                                           IF REQUIRED
                                                            Ex.PM issues Stage
                     RAM receives Stage 0                   0 feasibility drawing
                     feasibility drawing and                and cost appraisal (if
                       cost appraisal                       required) to RAM to
                                                           determine site suitability








                     RAM undertakes draft
                      Investment Appraisal
                     [IA] to determine if site
                     should be put forward
                         to LP&P
   14   15   16   17   18   19   20   21   22   23   24