Page 22 - 11394_AEW_XX_XX_PP_A_0003_CO-OP PRE-CONSTRUCTION MANUAL
P. 22

1











        1B.4 TCG led project





        Stage 2








        Stage 2 identifies the development of a

        project post Scheme Approval 1 through

        to exchange of contracts and Principal

        Contractor appointment.





             1.  Once approved at Scheme Approval 1 the RAM will engage solicitors and        11. The Quantity Surveyor will receive final Tender information from the
             agree the lease and the Internal Project Manager will appoint the Principal      Architect, Structural Engineer and Building Services Engineer following the
             Designer on behalf of TCG. Following appointment, the Principal Designer         Tender Review Meeting. Drawings and documentation will be collated and
             will conduct a desktop assessment of the current project information             issued to the Principal Contractors on the agreed Tender list for Tender
                                                                                              proposals to be developed and submitted
             2.  The External Project Manager will notify the project team (Architect,
             Quantity Surveyor and Format) of the project’s success through Scheme            12.  Once all Tender proposals have been received, a Post Tender
             Approval 1, obtain any outstanding hazardous materials reports (including        Qualification period commences until such a time that a Contractor
             asbestos) and procure Structural Engineer, Building Services Engineer and        Recommendation can be made jointly by the External Project Manager and
             Planning Consultant                                                              Quantity Surveyor

             3.  The External Project Manager will arrange a design team meeting,             13.  The External Project Manager will then update PCSD’s 01-04, complete
             assembling the project team to review the current project information and        PCSD 05 and issue to the Quantity Surveyor to produce the CV2 cost
             outline the next steps of the project                                            document and subsequently collate the package of information required
                                                                                              for Scheme Approval 2 and issue to the External Project Manager for their
                                                                                              approval and comments
             4.  Following the design team meeting the Principal Designer will produce
             a site inspection report, collate the available Pre-Construction Information     14.  Once agreed the External Project Manager will submit the project for
             and issue to the External Project Manager, highlighting absent information /     Scheme Approval 2. The External Project Manager and Quantity Surveyor
             documentation required to complete the PCI. The External Project Manager         will be present at the Scheme Approval 2 meeting
             will then be responsible for the procurement of all outstanding information
                                                                                              15.  Should the project be approved at Scheme Approval 2 the Quantity
             5.  Working collaboratively and in conjunction with each other, the Architect,   Surveyor will issue the approved Stage 2 pack and CV2 Investment
             Structural Engineer, Building Services Engineer and Planning Consultant          Appraisal [IA] summary to the RAM during the meeting
             will prepare co-ordinated drawings and information for the submission of
             planning application(s)                                                          16.  Following the meeting, the Internal Project Manager will complete and
                                                                                              issue the meeting minutes to the team (RAM, External Project Manager,
             6.  The External Project Manager will notify the Format team to review and       Quantity Surveyor, Architect, Principal Designer and Format)
             approve the proposed advertisements design co-ordinate the Asset Plan
             upon receipt of the Architects planning drawings                                 17.   If the CV2 Cost Plan is less than the CV1 Cost Plan, the project will
                                                                                              proceed to exchange of contracts by the RAM
             7.  Following receipt of all co-ordinated information, the External Project
             Manager will instruct the Planning Consultant to submit application(s) to        18.  If the CV2 Cost Plan is greater than the CV1 Cost Plan, the External
             Local Planning Authority and monitor through to decision. The Planning           Project Manager will escalate the approved Stage 2 pack to the RAM and
             Consultant will issue the decision notices to the External Project Manager,      Internal Project Manager for a Cost Plan review
             Architect and Principal Designer
                                                                                              19.  Should the CV2 Cost Plan be greater than +5% of that approved at CV1
             8.  Once planning consent has been obtained, the External Project Manager        or outside of a 12-month board approval date, the project will be represented
             will instruct the Architect, Structural Engineer and Building Services           at FCEF. FCEF approval is required for the project to proceed to exchange
             Engineer to prepare the relevant drawings / information to enable the            of contracts
             Quantity Surveyor to invite Principal Contractors to Tender for the project.
                                                                                              20.  Should the CV2 Cost Plan exceed board approval >5% of the approved
             9.  During the Tender documentation preparation period, a design team            CV1 costs, the project will be escalated to the Head of Acquisitions for
             meeting will be arranged by the External Project Manager, attended by            DAL uplift. The Head of Acquisitions approval is required for the project to
             The Construction Manager, Internal Project Manager, Quantity Surveyor,           proceed to exchange of contracts
             Architect, Principal Designer, Structural Engineer and Building Services
             Engineer. Following the meeting, the Internal and External Project Managers      21.  Following exchange of contracts, the External Project Manager will
             will agree the Tender list / programme respectively, the Quantity Surveyor       issue an Exchange pack of information to the Construction Manager
             will produce Employer’s Requirements [ER’s] and the design team will             (including agreed Tender drawings and PCSD 06) and arrange the
             finalize Tender drawings / information.                                          Exchange Meeting. Information pack to be issued min. 1 week prior to the
                                                                                              Exchange Meeting
             10.  A review meeting will be arranged to examine the finalized tender
             information, following which the Quantity Surveyor will collate the required     22.  The Exchange Meeting (held on-site for conversions only) will be
             information for the Tender document and issue to the prospective Principal       attended by the Construction Manager, RAM, Internal Project Manager and
             Contractors on the tender list. Review meeting to be attended by the             External Project Manager
             Construction Manager, External Project Manager, Quantity Surveyor,
             Architect, Principal Designer, Structural Engineer and Building Services         23.  Once the Exchange Meeting has been undertaken, the Construction
             Engineer                                                                         Manager will select and appoint the Principal Contractor



         1B.4   TCG led project                   Stage 2                              0.0                                   11.10.19