Page 22 - 11394_AEW_XX_XX_PP_A_0003_CO-OP PRE-CONSTRUCTION MANUAL
P. 22
1
1B.4 TCG led project
Stage 2
Stage 2 identifies the development of a
project post Scheme Approval 1 through
to exchange of contracts and Principal
Contractor appointment.
1. Once approved at Scheme Approval 1 the RAM will engage solicitors and 11. The Quantity Surveyor will receive final Tender information from the
agree the lease and the Internal Project Manager will appoint the Principal Architect, Structural Engineer and Building Services Engineer following the
Designer on behalf of TCG. Following appointment, the Principal Designer Tender Review Meeting. Drawings and documentation will be collated and
will conduct a desktop assessment of the current project information issued to the Principal Contractors on the agreed Tender list for Tender
proposals to be developed and submitted
2. The External Project Manager will notify the project team (Architect,
Quantity Surveyor and Format) of the project’s success through Scheme 12. Once all Tender proposals have been received, a Post Tender
Approval 1, obtain any outstanding hazardous materials reports (including Qualification period commences until such a time that a Contractor
asbestos) and procure Structural Engineer, Building Services Engineer and Recommendation can be made jointly by the External Project Manager and
Planning Consultant Quantity Surveyor
3. The External Project Manager will arrange a design team meeting, 13. The External Project Manager will then update PCSD’s 01-04, complete
assembling the project team to review the current project information and PCSD 05 and issue to the Quantity Surveyor to produce the CV2 cost
outline the next steps of the project document and subsequently collate the package of information required
for Scheme Approval 2 and issue to the External Project Manager for their
approval and comments
4. Following the design team meeting the Principal Designer will produce
a site inspection report, collate the available Pre-Construction Information 14. Once agreed the External Project Manager will submit the project for
and issue to the External Project Manager, highlighting absent information / Scheme Approval 2. The External Project Manager and Quantity Surveyor
documentation required to complete the PCI. The External Project Manager will be present at the Scheme Approval 2 meeting
will then be responsible for the procurement of all outstanding information
15. Should the project be approved at Scheme Approval 2 the Quantity
5. Working collaboratively and in conjunction with each other, the Architect, Surveyor will issue the approved Stage 2 pack and CV2 Investment
Structural Engineer, Building Services Engineer and Planning Consultant Appraisal [IA] summary to the RAM during the meeting
will prepare co-ordinated drawings and information for the submission of
planning application(s) 16. Following the meeting, the Internal Project Manager will complete and
issue the meeting minutes to the team (RAM, External Project Manager,
6. The External Project Manager will notify the Format team to review and Quantity Surveyor, Architect, Principal Designer and Format)
approve the proposed advertisements design co-ordinate the Asset Plan
upon receipt of the Architects planning drawings 17. If the CV2 Cost Plan is less than the CV1 Cost Plan, the project will
proceed to exchange of contracts by the RAM
7. Following receipt of all co-ordinated information, the External Project
Manager will instruct the Planning Consultant to submit application(s) to 18. If the CV2 Cost Plan is greater than the CV1 Cost Plan, the External
Local Planning Authority and monitor through to decision. The Planning Project Manager will escalate the approved Stage 2 pack to the RAM and
Consultant will issue the decision notices to the External Project Manager, Internal Project Manager for a Cost Plan review
Architect and Principal Designer
19. Should the CV2 Cost Plan be greater than +5% of that approved at CV1
8. Once planning consent has been obtained, the External Project Manager or outside of a 12-month board approval date, the project will be represented
will instruct the Architect, Structural Engineer and Building Services at FCEF. FCEF approval is required for the project to proceed to exchange
Engineer to prepare the relevant drawings / information to enable the of contracts
Quantity Surveyor to invite Principal Contractors to Tender for the project.
20. Should the CV2 Cost Plan exceed board approval >5% of the approved
9. During the Tender documentation preparation period, a design team CV1 costs, the project will be escalated to the Head of Acquisitions for
meeting will be arranged by the External Project Manager, attended by DAL uplift. The Head of Acquisitions approval is required for the project to
The Construction Manager, Internal Project Manager, Quantity Surveyor, proceed to exchange of contracts
Architect, Principal Designer, Structural Engineer and Building Services
Engineer. Following the meeting, the Internal and External Project Managers 21. Following exchange of contracts, the External Project Manager will
will agree the Tender list / programme respectively, the Quantity Surveyor issue an Exchange pack of information to the Construction Manager
will produce Employer’s Requirements [ER’s] and the design team will (including agreed Tender drawings and PCSD 06) and arrange the
finalize Tender drawings / information. Exchange Meeting. Information pack to be issued min. 1 week prior to the
Exchange Meeting
10. A review meeting will be arranged to examine the finalized tender
information, following which the Quantity Surveyor will collate the required 22. The Exchange Meeting (held on-site for conversions only) will be
information for the Tender document and issue to the prospective Principal attended by the Construction Manager, RAM, Internal Project Manager and
Contractors on the tender list. Review meeting to be attended by the External Project Manager
Construction Manager, External Project Manager, Quantity Surveyor,
Architect, Principal Designer, Structural Engineer and Building Services 23. Once the Exchange Meeting has been undertaken, the Construction
Engineer Manager will select and appoint the Principal Contractor
1B.4 TCG led project Stage 2 0.0 11.10.19