Page 12 - McD_Acrelec NGK32 Pre Installation V1.0 14.03.14_Neat
P. 12

Kiosk     Floor Construction  Ceiling Construction  Wall Construction  Height From Floor To
Location  (Wood? Concrete?       (False ceiling?                            Ceiling (mm)
                                   Wood? etc)
    1              etc)
    2
    3
    4
    5

For Double Sides Kiosks NGK 32” installed by Ceiling :
The nature of the ceiling must be recorded to ensure the installation engineers have the correct
equipment to make the necessary holes through which the cables may be routed to the kiosk.

There must be no other services plant or cables in the ceiling at the kiosk location that may be
damaged when the holes are cut.

For Double Sides Kiosks NGK 32” installed by ground :
The nature of the floor construction must be recorded so the installation engineers have the correct
equipment to drill into the floor and anchor the kiosks. Wooden or false floors will need to be
strengthened around the location of the kiosk to avoid the kiosk becoming loose during use or be
able to flex the floor through use. The floor area must be solid. There must be no under floor
heating or other services under the floor that may be damaged when the holes to anchor the kiosks
are drilled. If the cables are routed through the floor they must be installed in advance.

For Wall Mounted Kiosks NGK 32” installed by wall :
The nature of the wall construction must allow fixing the kiosk to the wall according to the fact that
the weight is 90kg. The kiosk will be fixed to the wall, all the cabling has to be completed before the
onsite installation.

                                                                       12 | P a g e