B     Works in Progress                                                                                (Rs. In '000s)
             Year of                      Name of work                                                                                Remarks
              sanc                                                                  PH           Cost         TDC
                                                                                                                       Civil- The work is preclosed due to
                                                                                                                       paucity of Funds.  Revised Estimate with
                                                                                                                       DSR2019 is prepred and  sent to Finance
                      Ramagundam~~Ramagundam Freight Depot- Creation                                                   on 01.06.2022.  Revised estimate was
              18-19   of facilities for carrying out maintenance of stainless steel   WS     76628           Mar'23    sanctioned on 09.07.22.  Tender
                      wagons.
                                                                                                                       Opened on 27.10.22 Under finalisation.
                                                                                                                       Elec: LOA issued. Work will be executed
                                                                                                                       on par with the Civil engg works.

                                                                                    WS Total    76628

              18-19   Provision of 2 Lifts at Ramagundam station                    PA       10909        completed    Work  completed.

              22-23   Installation of 32 OSOP stalls at 23 stations over SC Division  PA         812         Mar'23    Work is in progress.

                                                                                    PA total    11721
      40


                                                                                                            Summary(Fig in 000's)

                                                                                                  PH       Completed    In progress     Total

                                                                                                  TF         14113        76628         90741

                                                                                                 SW          27130           0          27130

                                                                                                 WS          129825          0         129825

                                                                                                  PA         10083        11721         21804

                                                                                               G Total       181151       88349        269500