Page 145 - Mines Facilities Plan
P. 145

ve (5)                                                                139
                                                  additional gensets in the future, which could bring the maximum capacity of
                                             two (2) additional gensets, which would bring the total capacity to 8.1 MW.
                                          gensets installed. As a result, the ISOC generator plant can readily accept
                                               In addition, it appears to be possible to add another PowerBlock with fi
















                                                     the ISOC generator plant to 11.3 MW.                             Existing Conditions




















                                                                                     a 0.87 power factor, Xcel Energy is able to supply up to an additional 5.5 MW
                                                                                  demand for the past year was 6.4 MW. Based on that demand and assuming
                                                 Substation. In 2018 a generator plant was installed as part of an Interruptible
                                              The Mines campus is fed by an Xcel Energy electrical system from Lookout
                                                                The campus medium voltage electrical distribution system includes two (2)
                                                    Service Option Credit (ISOC), which allows Xcel Energy to shed the Mines
                                                                                               (gensets) were installed, providing a total capacity of 6.9 MW. The gensets
                                                                      Loop 2A/2B primarily serves campus buildings south of 17th Street to 19th
                                                                                                 are grouped into “PowerBlocks”, with each PowerBlock having capacity for
                                                         served by Mines’ ISOC generator plant and is disconnected from the Xcel
                                                                   loops. Loop 1A/1B primarily serves campus buildings north of 17th Street.
                                                                                            As part of the ISOC project, a total of thirteen (13) engine-generator sets
                                                                                                      five (5) gensets. PowerBlock #1 currently has three (3) of five (5) possible















                                           ELECTRIC POWER  load during periods of peak demand. During these times, the campus is   Energy service.   Street. Loop 2A/2B will serve the future campus expansion. Based on the 600A primary meter rating, the maximum capacity of Xcel  Energy’s service to Mines is 13.7 MVA, and the campus peak electrical   of load from the existing medium voltage service.
   140   141   142   143   144   145   146   147   148   149   150