Page 181 - Mines Facilities Plan
P. 181

LOW PRIORITY   (54 CLASSROOMS)  Alderson Hall (9)       Berthoud Hall (4)       Brown Hall (16)       Chauvenet Hall (1)       Coolbaugh Hall (2)       CoorsTek (3)       Center for        Technology and   Learning Media (6)  Engineering Hall and        Annex (4)  Hill Hall (2)       Marquez Hall (11)       175







                                              MODERATE PRIORITY (13   CLASSROOMS)  Alderson Hall (4)       Berthoud Hall (1)       Chauvenet Hall (1)       Center for        Technology and   Learning Media (1)  Hill Hall (1)       Marquez Hall (1)       Stratton Hall (4)       The Plan














                                              IMMEDIATE PRIORITY (6   CLASSROOMS)  Alderson Hall (2)       Coolbaugh Hall (2)       General Research        Lab (1)  Hill Hall (1)     












                                                         and the same educational delivery infrastructure so that faculty and students
                                                      are necessary if Mines seeks that all classrooms will have the same quality
                                                            can expect a state-of-the-art learning environment in every classroom, and
                                                   classrooms and recommended room-level renovations. These renovations
                                                                         Mines should incrementally renovate nearly 80 existing classrooms. The
                                                               if Mines is moving toward a lower faculty-to-student ratio and a smaller
                                                 The master planning team conducted a detailed analysis of all existing




                                                                              Classroom Assessment Report (see Appendix 1) identified classrooms that  need various levels of architectural upgrades, IT/AV/electrical upgrades, and/ or furnishing upgrades. The analysis split the recommended renovations into



                                          CLASSROOM UPGRADE RENOVATIONS


















                                              THE NEED           classroom size.   THE PROJECT  three phases.  Necessary precedent projects: None  Enabled projects: None  THE SITE  N/A. Redevelopment