SCRUM











            In this example the application is an online banking system.


         The project has been broken down into a number of functions


        which are in the backlog. They are, get statement, pay in, pay

                                                                                           out.




               The whole team works on the “get statement” for a sprint

           period. At the end of the period, if the function pass test it is


              published. If it does not pass test and cannot be remedied


           quickly, lessons are learned and it goes back in the backlog.


         Over the course of the development, the lessons learned help

                                                   to resolve the difficult problems.













       © 2016 Engage ESM All Rights Reserved