Page 4 - ROYAL VIEW BILLING REQUEST
P. 4
MPW CORPORATION
M PLUMBING WORK
0009 MAKABUD ST., AMPARO SUBD., CALOOCAN CITY
Cel: 0922-817-3953 ; 09178491063
14-Mar-23
ATTENTION : SIR ROD
SUBJECT : BILLING FOR ADDITIONAL WORK NO. 1
RE: PROP. ROYAL VIEW GARDEN
@ BRGY DON GALO, PARANAQUE CITY
B// INSTALLATION OF ACU DRAIN EMERALD
Item Description Quantity Unit Unit Cost Material Cost Labor Cost Amount
40mm Pipe 33 lm 96.00 3,168.00 950.40 4,118.40
32mm Pipe 28 lm 83.00 2,324.00 697.20 3,021.20
32mm X 1/2 Insulation 18 lm 118.00 2,124.00 637.20 2,761.20
32mm Elbow 18 pc/s 16.00 288.00 86.40 374.40
40mm Elbow 16 pc/s 23.00 368.00 110.40 478.40
32mm Tee 3 pc/s 26.00 78.00 23.40 101.40
40mm Tee 3 pc/s 32.00 96.00 28.80 124.80
400cc Solvent Cement 2 pc/s 175.00 350.00 105.00 455.00
Subtotal: 8,796.00 2,638.80 11,434.80
TOTAL MATERIAL COST: 8,796.00
TOTAL LABOR COST: 2,638.80
PIPE SLEEVE FOR ACU COPPER PIPE : 2,000.00
HANGER, BRACKET, CONSUMABLE & CONTIGENCY: 3,000.00
CHIPPING WORKS AND SUPERVISION : 2,465.22
VAT: 2,268.02
TOTAL COST FOR ONE UNIT: 21,168.04
GRAND TOTAL COST FOR 58 UNIT: 1,227,746.32
TERMS AND CONDITION
30% Down payment and balance as per progress billing
We hope that this quotation will find satisfactory to you.
Thank you very much and I remain.
Very truly yours,
M-PLUMBING WORK
MICHAEL LIMQUECO
Contractor