Page 8 - ROYAL VIEW BILLING REQUEST
P. 8

MPW CORPORATION



                                                    M PLUMBING WORK



                                      0009 MAKABUD ST., AMPARO SUBD., CALOOCAN CITY
                                                  Cel: 0922-817-3953 ; 09178491063
          14-Mar-23
          ATTENTION             :            SIR ROD
          SUBJECT               :           BILLING FOR CHANGE  WORK  NO. 3
                                            RE: PROP. ROYAL VIEW GARDEN
                                             @ BRGY DON GALO, PARANAQUE CITY




      1// RELOCATION OF BAR SINK STUB OUT
                    Item Description         Quantity  Unit    Unit Cost    Material Cost    Labor Cost    Amount
          2"         PVC Pipe                  93    lm                     83.00                7,719.00              2,315.70             10,034.70
          2x90       PVC Elbow                 58    pc/s                   27.00                1,566.00                  469.80               2,035.80
          400cc      Solvent Cement            10    pc/s                 175.00                1,750.00                  525.00               2,275.00
          20mm       Pipe                      56    lm                     70.00                3,920.00              1,568.00               5,488.00
          20mm x 1/2" Female Elbow             20    pc/s                   80.00                1,600.00                  640.00               2,240.00
          20mm       Elbow                     28    pc/s                   11.00                    308.00                  123.20                  431.20
          20mm       Coupling                  58    lm                        7.00                    406.00                  162.40                  568.40
                                                                Subtotal:             17,269.00              5,804.10             23,073.10

                                                                             TOTAL MATERIAL COST:          17,269.00
                                                                                TOTAL LABOR COST:            5,804.10
                                                    HANGER, BRACKET,  CONSUMABLE & CONTIGENCY:          15,000.00
                                                                                  CHIPPING WORKS:            8,000.00
                                                                                               VAT:            3,926.90
                                                                           TOTAL ADDITIONAL COST:          50,000.00


          TERMS AND CONDITION
          30% Down payment and balance as per progress billing

          We hope that this quotation will find satisfactory to you.

          Thank you very much and I remain.


          Very truly yours,

          M-PLUMBING WORK



          MICHAEL LIMQUECO
                    Contractor