Page 8 - ROYAL VIEW BILLING REQUEST
P. 8
MPW CORPORATION
M PLUMBING WORK
0009 MAKABUD ST., AMPARO SUBD., CALOOCAN CITY
Cel: 0922-817-3953 ; 09178491063
14-Mar-23
ATTENTION : SIR ROD
SUBJECT : BILLING FOR CHANGE WORK NO. 3
RE: PROP. ROYAL VIEW GARDEN
@ BRGY DON GALO, PARANAQUE CITY
1// RELOCATION OF BAR SINK STUB OUT
Item Description Quantity Unit Unit Cost Material Cost Labor Cost Amount
2" PVC Pipe 93 lm 83.00 7,719.00 2,315.70 10,034.70
2x90 PVC Elbow 58 pc/s 27.00 1,566.00 469.80 2,035.80
400cc Solvent Cement 10 pc/s 175.00 1,750.00 525.00 2,275.00
20mm Pipe 56 lm 70.00 3,920.00 1,568.00 5,488.00
20mm x 1/2" Female Elbow 20 pc/s 80.00 1,600.00 640.00 2,240.00
20mm Elbow 28 pc/s 11.00 308.00 123.20 431.20
20mm Coupling 58 lm 7.00 406.00 162.40 568.40
Subtotal: 17,269.00 5,804.10 23,073.10
TOTAL MATERIAL COST: 17,269.00
TOTAL LABOR COST: 5,804.10
HANGER, BRACKET, CONSUMABLE & CONTIGENCY: 15,000.00
CHIPPING WORKS: 8,000.00
VAT: 3,926.90
TOTAL ADDITIONAL COST: 50,000.00
TERMS AND CONDITION
30% Down payment and balance as per progress billing
We hope that this quotation will find satisfactory to you.
Thank you very much and I remain.
Very truly yours,
M-PLUMBING WORK
MICHAEL LIMQUECO
Contractor