Page 6 - ROYAL VIEW BILLING REQUEST
P. 6
MPW CORPORATION
M PLUMBING WORK
0009 MAKABUD ST., AMPARO SUBD., CALOOCAN CITY
Cel: 0922-817-3953 ; 09178491063
14-Mar-23
ATTENTION : SIR ROD
SUBJECT : BILLING FOR CHANGE ORDER NO. 2
RE: PROP. ROYAL VIEW GARDEN
@ BRGY DON GALO, PARANAQUE CITY
1// REVISED BALCONY DRAIN & BAR SINK @ 4TH FLOOR
Item Description Quantity Unit Unit Cost Material Cost Labor Cost Amount
50mm Pipe 4 lm 83.00 332.00 99.60 431.60
75mm Pipe 2 lm 179.00 358.00 107.40 465.40
3X2 Wye 2 pc/s 105.00 210.00 63.00 273.00
2x90 Elbow 3 pc/s 27.00 81.00 24.30 105.30
2X45 Elbow 4 pc/s 22.00 88.00 26.40 114.40
400cc Solvent Cement 1 pc/s 175.00 175.00 52.50 227.50
Subtotal: 1,244.00 373.20 1,617.20
TOTAL MATERIAL COST: 1,244.00
TOTAL LABOR COST: 373.20
CHIPPING WORKS: 1,200.00
HANGER, BRACKET, CONSUMABLE & CONTIGENCY: 422.58
TOTAL COST FOR ONE UNIT: 3,239.78
TOTAL COST FOR 29 UNIT INSTALLED: 93,953.62
CHIPPING AND RESTORATION FOR UNITS ON HOLD (10 UNITS): 12,000.00
TOTAL ADDITIONAL COST: 105,953.62
TERMS AND CONDITION
30% Down payment and balance as per progress billing
We hope that this quotation will find satisfactory to you.
Thank you very much and I remain.
Very truly yours,
M-PLUMBING WORK
MICHAEL LIMQUECO
Contractor