 4 STRATEGIC INITIATIVES




 Strategy   Winning   Breaking   Agility through                             04
 Execution  Mindset  the Silos  Efficiency  •  Purchase  to  Pay  (P2P)  Process  Efficiency
 Improvement:
 Leader: Fucai W. / Kevin S.  Leader: Julie Z. / Frank C.  Leader: Hervé / Robert Y.  Leader: Cheral Z. / Kader
 th
   - Project kicked off on Oct. 31 , 2016. Project objective, scope,
 team structure, timeline plan were defined. Pre-study on domains
 of Raw Materials, Goods and Services, and Logistics Services
 were conducted
   - An in-house training of Selective Six Sigma and Lean Tools
 Introduction was delivered to the project team members on Nov.
 th
 23 , 2016
 Objective & How:    - ACF and ADAF are selected as pilot companies and currently
 Objective:  Objective:  Objective:  Decrease time spent on   in the stage of preparation and assessment, which include ticket   ARKEMA & ME
 Growing 1 b€ of additional   Implement a collective   To go faster through better   internal processes and   analysis; open dialogue; SAP data evaluation; processes flowchart;
 revenue over by year 2020   culture change that fully   efficiency of processes and   procedures:  and questionnaire.
 (organic growth 0.5b€ +   supports our APAC growth   alignment between BU and   -P to P process: Identify     - Designing KPIs and progress update dashboard
 M&A)  ambition  central functions  opportunities to increase     - Identifying quick wins:
 processes/operational efficiencies;      ·Purchase Requisition (PR) create right after purchasing
 How:  How:  How:  Define KPIs for continuing   needs arisen
 monitoring      (Leader: Jocelyn C.)
 -Set up B1 Club, develop   -4 values promotion  -Reach Service Level   -Expense claim: reduce time to      ·Optimize Goods Receipt (GR) process (target is to change
 new ideas through regional   -Employees' engagement   Agreement between central   rolling 4 weeks after complied   from two steps to one step)  disCOVer arkeMa
 BU networking, BU leaders   survey (every 2 years)  functions and BUs  application       (Leader: Brian W.)     ·Update Webcycle Workflow trigger mechanism
 meet in regular base  -Policies & regulations  -Cross Function platforms  -Budget: decrease the No. of
 -Set up M&A project team  -Trainings & workshops  revisions and align with time frame   Forane® and U
 and sequence from different
 functions            (Leader: Penny Y.;   •  Expense Claim Process:
 Co-leader: Hong P.)
   - Standardized policies and procedure
   - The average expense claim processing time is reducing to 10
 days if the quality of claim is good